Power by county

Colusa, CA: data center power outlook

Colusa, California is served through the CAISO market (California Independent System Operator), and the figures below describe the public grid around a prospective data center site there. Colusa carries 21 mapped substations within its boundary, and the highest reachable grid access is 500 kV. Service in Colusa spans 2 utilities, with PACIFIC GAS & ELECTRIC CO., WAPA-- WESTERN AREA POWER ADMINISTRATION among those mapped.

Grid position at a glance

Serving utilities
PACIFIC GAS & ELECTRIC CO., WAPA-- WESTERN AREA POWER ADMINISTRATION
ISO / market
CAISO (California Independent System Operator)
Highest grid access
500 kV
Substations in county
21
Industrial retail rate
21.6¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
2 serving utilities: 2.9 to 21.1¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
369 lb CO2/MWh
Water withdrawals
699 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
98,555 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Colusa

What follows is a screening-grade read of Colusa, California, built only from named public datasets. Grid access in Colusa extends to 500 kV, a high-voltage line class. The mapped layer packs 21 substations into Colusa, a dense spread of options.

Interconnection over Colusa runs through the CAISO market (California Independent System Operator) and its rules. For Colusa, the rate shown is the state industrial average of 21.6 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Colusa that report an industrial rate span 2 serving utilities: 2.9 to 21.1¢/kWh, shown as context and never as the county rate.

The covered queue feeds list nothing for Colusa, California, which may be quiet or simply uningested. Nothing is on file for Colusa, California in EIA-860M as planned or under construction, which counts as a measured zero. Colusa sits under a balancing authority that eGRID puts at 369.346 lb CO2 per MWh.

Colusa withdrew 699.37 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 98,555 people are employed in construction within a 120 km commute of Colusa (BLS QCEW), which frames staffing distance rather than free labour.

For Colusa, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Colusa, California describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Colusa, California, a specific address needs its own interconnection study, which this page does not attempt. The figures for Colusa, California refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.

Sources