Power by county

Broomfield, CO: data center power outlook

The grid around Broomfield, Colorado is summarized here from public data, starting from the county's position in an area outside an organized wholesale market. Inside Broomfield the mapped layer shows 4 mapped substations, with grid access reaching 230 kV at its strongest point. Retail service across Broomfield is split among 3 utilities, among them PUBLIC SERVICE CO OF COLORADO, UNITED POWER, INC, WAPA-- WESTERN AREA POWER ADMINISTRATION.

Grid position at a glance

Serving utilities
PUBLIC SERVICE CO OF COLORADO, UNITED POWER, INC, WAPA-- WESTERN AREA POWER ADMINISTRATION
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
230 kV
Substations in county
4
Industrial retail rate
9.1¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 serving utilities: 2.6 to 9.5¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
803 lb CO2/MWh
Water withdrawals
7.1 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
140,764 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Broomfield

Read on for the public power picture of Broomfield in Colorado, assembled for data center siting. Transmission-class access reaches 230 kV in Broomfield at its strongest mapped point. Broomfield, Colorado shows 4 substations in the mapped layer, a thin spread across the county.

No organized wholesale market covers Broomfield, Colorado, so capacity moves through the local utility and bilateral agreements. Broomfield carries the state industrial average retail rate of 9.1 cents per kWh from EIA-861, applied statewide. For Broomfield, the per-utility spread is 3 serving utilities: 2.6 to 9.5¢/kWh, which qualifies but never replaces the state average.

For Broomfield, Colorado, no queued project appears in the feeds currently covered. For Broomfield, Colorado, the EIA-860M inventory shows no planned or under-construction generation, a measured absence. In eGRID, the balancing authority over Broomfield shows 802.655 lb CO2 per MWh.

For Broomfield, the USGS 2015 compilation records 7.05 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Broomfield sits within commuting range of roughly 140,764 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Broomfield here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Broomfield, Colorado settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Broomfield, Colorado requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Broomfield, Colorado are logged directly below, so each figure on this page can be traced back to its public dataset.

Sources