The grid around Gilpin, Colorado is summarized here from public data, starting from the county's position in an area outside an organized wholesale market. Inside Gilpin the mapped layer shows 3 mapped substations, with grid access reaching 69 kV at its strongest point. Retail service across Gilpin is split among 4 utilities, among them MOUNTAIN PARKS ELECTRIC, INC, PUBLIC SERVICE CO OF COLORADO, UNITED POWER, INC.
Grid position at a glance
- Serving utilities
- MOUNTAIN PARKS ELECTRIC, INC, PUBLIC SERVICE CO OF COLORADO, UNITED POWER, INC, WAPA-- WESTERN AREA POWER ADMINISTRATION
- ISO / market
- NON_ISO (Not in an organized wholesale market)
- Highest grid access
- 69 kV
- Substations in county
- 3
- Industrial retail rate
- 9.1¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 4 serving utilities: 2.6 to 9.5¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 803 lb CO2/MWh
- Water withdrawals
- 0.9 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 143,405 employed in construction within ~120 km (17 of 18 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Gilpin
Read on for the public power picture of Gilpin in Colorado, assembled for data center siting. Grid access in Gilpin peaks at 69 kV, below the transmission class most large loads look for. Across Gilpin, Colorado, the mapped layer holds just 3 substations, so options gather at a handful of places.
No organized wholesale market covers Gilpin, Colorado, so capacity moves through the local utility and bilateral agreements. Gilpin carries the state industrial average retail rate of 9.1 cents per kWh from EIA-861, applied statewide. For Gilpin, the per-utility spread is 4 serving utilities: 2.6 to 9.5¢/kWh, which qualifies but never replaces the state average.
Gilpin, Colorado has nothing in the interconnection queue across the feeds covered here, quiet or uningested. For Gilpin, Colorado, the EIA-860M inventory shows no planned or under-construction generation, a measured absence. In eGRID, the balancing authority over Gilpin shows 802.655 lb CO2 per MWh.
For Gilpin, the USGS 2015 compilation records 0.9 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Gilpin sits within commuting range of roughly 143,405 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.
Every figure for Gilpin here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Gilpin, Colorado settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Gilpin, Colorado requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Gilpin, Colorado are logged directly below, so each figure on this page can be traced back to its public dataset.