Power by county

Park, CO: data center power outlook

Park, Colorado is served through an area outside an organized wholesale market, and the figures below describe the public grid around a prospective data center site there. Park carries 11 mapped substations within its boundary, and the highest reachable grid access is 230 kV. Service in Park spans 5 utilities, with BLACK HILLS COLORADO ELECTRIC, LLC, CORE ELECTRIC COOPERATIVE, PUBLIC SERVICE CO OF COLORADO among those mapped.

Grid position at a glance

Serving utilities
BLACK HILLS COLORADO ELECTRIC, LLC, CORE ELECTRIC COOPERATIVE, PUBLIC SERVICE CO OF COLORADO, SANGRE DE CRISTO ELEC ASSN INC, WAPA-- WESTERN AREA POWER ADMINISTRATION
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
230 kV
Substations in county
11
Industrial retail rate
9.1¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
4 of 5 serving utilities: 2.6 to 9.9¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
803 lb CO2/MWh
Water withdrawals
39 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
87,528 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Park

What follows is a screening-grade read of Park, Colorado, built only from named public datasets. At 230 kV, Park sits in the transmission class that a large load would look to. The mapped layer places 11 substations across Park, a moderate density.

Because Park, Colorado sits outside an organized market, capacity and interconnection are handled by the utility and bilateral deals, not a market operator. For Park, the rate shown is the state industrial average of 9.1 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Park that report an industrial rate span 4 of 5 serving utilities: 2.6 to 9.9¢/kWh, shown as context and never as the county rate.

No interconnection-queue project is on record for Park, Colorado in the covered feeds, which reflects either genuine quiet or a queue not yet ingested. Nothing is on file for Park, Colorado in EIA-860M as planned or under construction, which counts as a measured zero. Park sits under a balancing authority that eGRID puts at 802.655 lb CO2 per MWh.

Park withdrew 39.47 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 87,528 people are employed in construction within a 120 km commute of Park (BLS QCEW), which frames staffing distance rather than free labour.

For Park, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Park, Colorado describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Park, Colorado, a specific address needs its own interconnection study, which this page does not attempt. The figures for Park, Colorado refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.

Sources