Sumter, FL: data center power outlook

Sumter, Florida is served through an area outside an organized wholesale market, and the figures below describe the public grid around a prospective data center site there. Sumter carries 18 mapped substations within its boundary, and the highest reachable grid access is 500 kV. Service in Sumter spans 6 utilities, with CITY OF BUSHNELL - (FL), CITY OF LEESBURG - (FL), DUKE ENERGY FLORIDA, LLC among those mapped.

Grid position at a glance

Serving utilities
CITY OF BUSHNELL - (FL), CITY OF LEESBURG - (FL), DUKE ENERGY FLORIDA, LLC, SUMTER ELECTRIC COOP, INC, TAMPA ELECTRIC CO, WITHLACOOCHEE RIVER ELEC COOP
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
500 kV
Substations in county
18
Industrial retail rate
8.8¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
5 of 6 serving utilities: 5.4 to 13.4¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
1,208 lb CO2/MWh
Water withdrawals
36 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
238,215 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Sumter

What follows is a screening-grade read of Sumter, Florida, built only from named public datasets. Grid access in Sumter extends to 500 kV, a high-voltage line class. The mapped layer places 18 substations across Sumter, a moderate density.

Because Sumter, Florida sits outside an organized market, capacity and interconnection are handled by the utility and bilateral deals, not a market operator. For Sumter, the rate shown is the state industrial average of 8.8 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Sumter that report an industrial rate span 5 of 6 serving utilities: 5.4 to 13.4¢/kWh, shown as context and never as the county rate.

No interconnection-queue project is on record for Sumter, Florida in the covered feeds, which reflects either genuine quiet or a queue not yet ingested. Sumter, Florida has no EIA-860M generation on file, which reads as zero rather than as a gap. Sumter sits under a balancing authority that eGRID puts at 1,207.833 lb CO2 per MWh.

Sumter withdrew 35.99 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 238,215 people are employed in construction within a 120 km commute of Sumter (BLS QCEW), which frames staffing distance rather than free labour.

For Sumter, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Sumter, Florida describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Sumter, Florida, a specific address needs its own interconnection study, which this page does not attempt. The figures for Sumter, Florida refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.