Power by county

Bacon, GA: data center power outlook

For Bacon, Georgia, the public grid picture begins with its place in an area outside an organized wholesale market and the infrastructure mapped inside the county. Grid access across Bacon tops out at 230 kV, over a footprint of 3 mapped substations. In Bacon, 2 utilities share the retail territory, among them GEORGIA POWER CO, SATILLA RURAL ELEC MEMBER CORPORATION.

Grid position at a glance

Serving utilities
GEORGIA POWER CO, SATILLA RURAL ELEC MEMBER CORPORATION
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
230 kV
Substations in county
3
Industrial retail rate
7.8¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
2 serving utilities: 5.1 to 7.1¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
300 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
843 lb CO2/MWh
Water withdrawals
6.0 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
16,075 employed in construction within ~120 km (36 of 39 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Bacon

This page gathers the public grid evidence for Bacon, Georgia that bears on a large new load. The strongest mapped access in Bacon is 230 kV, squarely transmission class. Across Bacon, Georgia, the mapped layer holds just 3 substations, so options gather at a handful of places.

Bacon, Georgia lies outside an organized wholesale market, so generation and transmission are arranged bilaterally and through the local utility rather than a central market operator. The state industrial average retail rate is 7.8 cents per kWh, drawn from EIA-861 and applied to Bacon at the state level rather than as a county rate. The serving utilities in Bacon that publish a rate range 2 serving utilities: 5.1 to 7.1¢/kWh, a spread kept separate from the state average.

Bacon, Georgia has nothing in the interconnection queue across the feeds covered here, quiet or uningested. Federal filings (EIA-860M) list 300 MW of generation as planned or under construction in Bacon. Grid carbon intensity for Bacon, via its balancing authority, is 842.741 lb CO2 per MWh in eGRID.

USGS 2015 puts freshwater withdrawals across Bacon at 6.04 million gallons per day for all uses, a measure of use, not spare supply. Within roughly a 120 km commute of Bacon, about 16,075 people are employed in construction (BLS QCEW), which speaks to how far crews for a multi-year build would travel, not to labour known to be free.

Read the Bacon figures as screening-grade context: they describe the surrounding grid, not a specific parcel. The numbers for Bacon, Georgia qualify one another, so grid access, substation density, market membership, and rate are meant to be read as a set, not in isolation. Past this screening view, siting in Bacon, Georgia turns on a study of a particular address, something no county-level page can stand in for. Every number shown for Bacon, Georgia traces to a public source listed below, with its retrieval date, so the provenance is auditable rather than asserted.

Sources