Clinch, GA: data center power outlook

The grid around Clinch, Georgia is summarized here from public data, starting from the county's position in an area outside an organized wholesale market. Inside Clinch the mapped layer shows 3 mapped substations, with grid access reaching 115 kV at its strongest point. Retail service across Clinch is split among 6 utilities, among them DUKE ENERGY FLORIDA, LLC, FLORIDA POWER & LIGHT CO, GEORGIA POWER CO.

Grid position at a glance

Serving utilities
DUKE ENERGY FLORIDA, LLC, FLORIDA POWER & LIGHT CO, GEORGIA POWER CO, OKEFENOKE RURAL EL MEMBER CORP, SATILLA RURAL ELEC MEMBER CORPORATION, SLASH PINE ELEC MEMBER CORP
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
115 kV
Substations in county
3
Industrial retail rate
7.8¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 of 6 serving utilities: 3.7 to 7.1¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
843 lb CO2/MWh
Water withdrawals
1.2 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
53,737 employed in construction within ~120 km (30 of 34 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Clinch

Read on for the public power picture of Clinch in Georgia, assembled for data center siting. Transmission-class access reaches 115 kV in Clinch at its strongest mapped point. Clinch, Georgia shows 3 substations in the mapped layer, a thin spread across the county.

Clinch, Georgia lies outside an organized wholesale market, so generation and transmission are arranged bilaterally and through the local utility rather than a central market operator. Clinch carries the state industrial average retail rate of 7.8 cents per kWh from EIA-861, applied statewide. For Clinch, the per-utility spread is 3 of 6 serving utilities: 3.7 to 7.1¢/kWh, which qualifies but never replaces the state average.

For Clinch, Georgia, no queued project appears in the feeds currently covered. The federal EIA-860M inventory files no planned or under-construction generation in Clinch, Georgia, a real zero rather than a gap. In eGRID, the balancing authority over Clinch shows 842.741 lb CO2 per MWh.

For Clinch, the USGS 2015 compilation records 1.15 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Clinch sits within commuting range of roughly 53,737 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Clinch here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Clinch, Georgia settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Clinch, Georgia requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Clinch, Georgia are logged directly below, so each figure on this page can be traced back to its public dataset.