Power by county
Colquitt, GA: data center power outlook
Colquitt, Georgia is served through an area outside an organized wholesale market, and the figures below describe the public grid around a prospective data center site there. Colquitt carries 27 mapped substations within its boundary, and the highest reachable grid access is 230 kV. Service in Colquitt spans 7 utilities, with CITY OF DOERUN - (GA), CITY OF MOULTRIE - (GA), COLQUITT ELECTRIC MEMBERSHIP CORP among those mapped.
Grid position at a glance
- Serving utilities
- CITY OF DOERUN - (GA), CITY OF MOULTRIE - (GA), COLQUITT ELECTRIC MEMBERSHIP CORP, CRISP COUNTY POWER COMM, GEORGIA POWER CO, GRADY ELECTRIC MEMBERSHIP CORP, MITCHELL ELECTRIC MEMBER CORP
- ISO / market
- NON_ISO (Not in an organized wholesale market)
- Highest grid access
- 230 kV
- Substations in county
- 27
- Industrial retail rate
- 7.8¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 4 of 7 serving utilities: 7.1 to 16.4¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 843 lb CO2/MWh
- Water withdrawals
- 27 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 19,773 employed in construction within ~120 km (30 of 37 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Colquitt
What follows is a screening-grade read of Colquitt, Georgia, built only from named public datasets. At 230 kV, Colquitt sits in the transmission class that a large load would look to. The mapped layer packs 27 substations into Colquitt, a dense spread of options.
Because Colquitt, Georgia sits outside an organized market, capacity and interconnection are handled by the utility and bilateral deals, not a market operator. For Colquitt, the rate shown is the state industrial average of 7.8 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Colquitt that report an industrial rate span 4 of 7 serving utilities: 7.1 to 16.4¢/kWh, shown as context and never as the county rate.
The covered queue feeds list nothing for Colquitt, Georgia, which may be quiet or simply uningested. Nothing is on file for Colquitt, Georgia in EIA-860M as planned or under construction, which counts as a measured zero. Colquitt sits under a balancing authority that eGRID puts at 842.741 lb CO2 per MWh.
Colquitt withdrew 26.84 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 19,773 people are employed in construction within a 120 km commute of Colquitt (BLS QCEW), which frames staffing distance rather than free labour.
For Colquitt, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Colquitt, Georgia describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Colquitt, Georgia, a specific address needs its own interconnection study, which this page does not attempt. The figures for Colquitt, Georgia refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.