Evans, GA: data center power outlook

Evans, Georgia is served through an area outside an organized wholesale market, and the figures below describe the public grid around a prospective data center site there. Evans carries 3 mapped substations within its boundary, and the highest reachable grid access is 115 kV. Service in Evans spans 3 utilities, with CANOOCHEE ELECTRIC MEMBER CORP, EXCELSIOR ELECTRIC MEMBER CORP, GEORGIA POWER CO among those mapped.

Grid position at a glance

Serving utilities
CANOOCHEE ELECTRIC MEMBER CORP, EXCELSIOR ELECTRIC MEMBER CORP, GEORGIA POWER CO
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
115 kV
Substations in county
3
Industrial retail rate
7.8¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 serving utilities: 7.1 to 14.1¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
843 lb CO2/MWh
Water withdrawals
5.5 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
21,877 employed in construction within ~120 km (32 of 34 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Evans

The material below frames Evans, Georgia for a prospective large load, drawing only on public sources. At 115 kV, Evans sits in the transmission class that a large load would look to. The mapped footprint in Evans, Georgia is sparse, 3 substations, so options cluster at those points.

Evans, Georgia is not inside an organized market, which leaves interconnection to the utility and bilateral contracts. For Evans, the rate shown is the state industrial average of 7.8 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Evans that report an industrial rate span 3 serving utilities: 7.1 to 14.1¢/kWh, shown as context and never as the county rate.

Across the covered feeds, Evans, Georgia carries no interconnection-queue project, from either real quiet or a feed not yet loaded. Evans, Georgia has no EIA-860M generation on file, which reads as zero rather than as a gap. Evans sits under a balancing authority that eGRID puts at 842.741 lb CO2 per MWh.

Evans withdrew 5.48 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 21,877 people are employed in construction within a 120 km commute of Evans (BLS QCEW), which frames staffing distance rather than free labour.

For Evans, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Evans, Georgia describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Evans, Georgia, a specific address needs its own interconnection study, which this page does not attempt. The figures for Evans, Georgia refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.