Power by county
Jenkins, GA: data center power outlook
Jenkins sits in an area outside an organized wholesale market; what follows is the screening-grade grid picture for Jenkins, Georgia, drawn from public datasets. Counting from the mapped infrastructure, Jenkins holds 4 mapped substations and reaches 115 kV. Jenkins is covered by 4 retail service territories, including EXCELSIOR ELECTRIC MEMBER CORP, GEORGIA POWER CO, JEFFERSON ELECTRIC MEMBER CORP.
Grid position at a glance
- Serving utilities
- EXCELSIOR ELECTRIC MEMBER CORP, GEORGIA POWER CO, JEFFERSON ELECTRIC MEMBER CORP, PLANTERS ELECTRIC MEMBER CORP
- ISO / market
- NON_ISO (Not in an organized wholesale market)
- Highest grid access
- 115 kV
- Substations in county
- 4
- Industrial retail rate
- 7.8¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 4 serving utilities: 7.1 to 15.5¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 843 lb CO2/MWh
- Water withdrawals
- 8.0 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 22,984 employed in construction within ~120 km (32 of 35 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Jenkins
Below, Jenkins in Georgia is described from public data as a starting point for siting diligence. Jenkins reaches 115 kV at its highest mapped voltage, a transmission class that can carry a substantial interconnection where capacity exists. Jenkins, Georgia carries a thin 4-substation footprint in the mapped layer, concentrating where a connection could land.
Because Jenkins, Georgia sits outside an organized market, capacity and interconnection are handled by the utility and bilateral deals, not a market operator. The rate for Jenkins is the 7.8 cents per kWh state industrial average (EIA-861), the same figure the map colours by. Across Jenkins, reported per-utility industrial rates cover 4 serving utilities: 7.1 to 15.5¢/kWh, offered only as context beneath the state figure.
The covered queue feeds list nothing for Jenkins, Georgia, which may be quiet or simply uningested. EIA-860M lists nothing planned or under construction for Jenkins, Georgia, which is a national filing and so a real zero. The balancing authority covering Jenkins carries a grid carbon intensity of 842.741 lb CO2 per MWh in eGRID.
Reported freshwater withdrawals for all uses in Jenkins are 8 million gallons per day in the USGS 2015 compilation, existing demand rather than water free for a new load. Around Jenkins, some 22,984 people work in construction within about a 120 km commute (BLS QCEW), a measure of reach, not of available crews.
These numbers for Jenkins are screening-grade context for the whole county, drawn from public data with the gaps left visible. Read the figures for Jenkins, Georgia together rather than one at a time: grid access matters less without substations near it, and a quiet queue reads differently inside an organized market than outside one. The next step for Jenkins, Georgia is an address-level interconnection study; the county figures here only narrow where to look. For Jenkins, Georgia, the source log below records where each figure comes from and when it was pulled, keeping the provenance visible.