McDuffie, GA: data center power outlook

McDuffie, Georgia is served through an area outside an organized wholesale market, and the figures below describe the public grid around a prospective data center site there. McDuffie carries 14 mapped substations within its boundary, and the highest reachable grid access is 500 kV. Service in McDuffie spans 3 utilities, with GEORGIA POWER CO, JEFFERSON ELECTRIC MEMBER CORP, RAYLE ELECTRIC MEMBERSHIP CORP among those mapped.

Grid position at a glance

Serving utilities
GEORGIA POWER CO, JEFFERSON ELECTRIC MEMBER CORP, RAYLE ELECTRIC MEMBERSHIP CORP
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
500 kV
Substations in county
14
Industrial retail rate
7.8¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 serving utilities: 7.1 to 8.7¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
250 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
843 lb CO2/MWh
Water withdrawals
3.6 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
27,521 employed in construction within ~120 km (33 of 36 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in McDuffie

The material below frames McDuffie, Georgia for a prospective large load, drawing only on public sources. Grid access in McDuffie extends to 500 kV, a high-voltage line class. The mapped layer places 14 substations across McDuffie, a moderate density.

Because McDuffie, Georgia sits outside an organized market, capacity and interconnection are handled by the utility and bilateral deals, not a market operator. For McDuffie, the rate shown is the state industrial average of 7.8 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving McDuffie that report an industrial rate span 3 serving utilities: 7.1 to 8.7¢/kWh, shown as context and never as the county rate.

The covered queue feeds list nothing for McDuffie, Georgia, which may be quiet or simply uningested. EIA-860M records 250 MW planned or under construction for McDuffie. McDuffie sits under a balancing authority that eGRID puts at 842.741 lb CO2 per MWh.

McDuffie withdrew 3.6 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 27,521 people are employed in construction within a 120 km commute of McDuffie (BLS QCEW), which frames staffing distance rather than free labour.

For McDuffie, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for McDuffie, Georgia describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in McDuffie, Georgia, a specific address needs its own interconnection study, which this page does not attempt. The figures for McDuffie, Georgia refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.