Power by county

Ware, GA: data center power outlook

Ware, Georgia is served through an area outside an organized wholesale market, and the figures below describe the public grid around a prospective data center site there. Ware carries 15 mapped substations within its boundary, and the highest reachable grid access is 230 kV. Service in Ware spans 5 utilities, with FLORIDA POWER & LIGHT CO, GEORGIA POWER CO, OKEFENOKE RURAL EL MEMBER CORP among those mapped.

Grid position at a glance

Serving utilities
FLORIDA POWER & LIGHT CO, GEORGIA POWER CO, OKEFENOKE RURAL EL MEMBER CORP, SATILLA RURAL ELEC MEMBER CORPORATION, SLASH PINE ELEC MEMBER CORP
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
230 kV
Substations in county
15
Industrial retail rate
7.8¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 of 5 serving utilities: 3.7 to 7.1¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
843 lb CO2/MWh
Water withdrawals
5.4 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
54,515 employed in construction within ~120 km (30 of 34 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Ware

The material below frames Ware, Georgia for a prospective large load, drawing only on public sources. At 230 kV, Ware sits in the transmission class that a large load would look to. The mapped layer places 15 substations across Ware, a moderate density.

Because Ware, Georgia sits outside an organized market, capacity and interconnection are handled by the utility and bilateral deals, not a market operator. For Ware, the rate shown is the state industrial average of 7.8 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Ware that report an industrial rate span 3 of 5 serving utilities: 3.7 to 7.1¢/kWh, shown as context and never as the county rate.

Across the covered feeds, Ware, Georgia carries no interconnection-queue project, from either real quiet or a feed not yet loaded. Nothing is on file for Ware, Georgia in EIA-860M as planned or under construction, which counts as a measured zero. Ware sits under a balancing authority that eGRID puts at 842.741 lb CO2 per MWh.

Ware withdrew 5.42 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 54,515 people are employed in construction within a 120 km commute of Ware (BLS QCEW), which frames staffing distance rather than free labour.

For Ware, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Ware, Georgia describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Ware, Georgia, a specific address needs its own interconnection study, which this page does not attempt. The figures for Ware, Georgia refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.