Grundy, IL: data center power outlook
For Grundy, Illinois, the public grid picture begins with its place in the PJM market (PJM Interconnection) and the infrastructure mapped inside the county. Grid access across Grundy tops out at 765 kV, over a footprint of 20 mapped substations. In Grundy, 3 utilities share the retail territory, among them AMEREN ILLINOIS COMPANY, COMMONWEALTH EDISON CO, CORN BELT ENERGY CORPORATION.
Grid position at a glance
- Serving utilities
- AMEREN ILLINOIS COMPANY, COMMONWEALTH EDISON CO, CORN BELT ENERGY CORPORATION
- ISO / market
- PJM (PJM Interconnection)
- Highest grid access
- 765 kV
- Substations in county
- 20
- Industrial retail rate
- 10.1¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 3 serving utilities: 1.6 to 7.4¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- 20 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 716 lb CO2/MWh
- Water withdrawals
- 456 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 181,259 employed in construction within ~120 km (24 of 25 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Grundy
For Grundy, Illinois, the following sections turn public grid records into a siting-oriented summary. The highest mapped voltage in Grundy is 765 kV, an extra-high-voltage line. Grundy carries 20 substations in the mapped layer, spread across the county.
For Grundy, the PJM market (PJM Interconnection) is the operator that handles interconnection and capacity. The state industrial average retail rate is 10.1 cents per kWh, drawn from EIA-861 and applied to Grundy at the state level rather than as a county rate. The serving utilities in Grundy that publish a rate range 3 serving utilities: 1.6 to 7.4¢/kWh, a spread kept separate from the state average.
Grundy, Illinois has nothing in the interconnection queue across the feeds covered here, quiet or uningested. Federal filings (EIA-860M) list 20 MW of generation as planned or under construction in Grundy. Grid carbon intensity for Grundy, via its balancing authority, is 716.09 lb CO2 per MWh in eGRID.
USGS 2015 puts freshwater withdrawals across Grundy at 456.04 million gallons per day for all uses, a measure of use, not spare supply. Within roughly a 120 km commute of Grundy, about 181,259 people are employed in construction (BLS QCEW), which speaks to how far crews for a multi-year build would travel, not to labour known to be free.
Read the Grundy figures as screening-grade context: they describe the surrounding grid, not a specific parcel. The numbers for Grundy, Illinois qualify one another, so grid access, substation density, market membership, and rate are meant to be read as a set, not in isolation. Past this screening view, siting in Grundy, Illinois turns on a study of a particular address, something no county-level page can stand in for. Every number shown for Grundy, Illinois traces to a public source listed below, with its retrieval date, so the provenance is auditable rather than asserted.