Power by county
Williamson, IL: data center power outlook
The grid around Williamson, Illinois is summarized here from public data, starting from the county's position in the MISO market (Midcontinent Independent System Operator). Inside Williamson the mapped layer shows 59 mapped substations, with grid access reaching 345 kV at its strongest point. Retail service across Williamson is split among 4 utilities, among them AMEREN ILLINOIS COMPANY, EGYPTIAN ELECTRIC COOP ASSN, SOUTHEASTERN IL ELEC COOP, INC.
Grid position at a glance
- Serving utilities
- AMEREN ILLINOIS COMPANY, EGYPTIAN ELECTRIC COOP ASSN, SOUTHEASTERN IL ELEC COOP, INC, SOUTHERN ILLINOIS ELEC COOP
- ISO / market
- MISO (Midcontinent Independent System Operator)
- Highest grid access
- 345 kV
- Substations in county
- 59
- Industrial retail rate
- 10.1¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 2 of 4 serving utilities: 1.6 to 10.4¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- 3 projects, 640 MW
- Proposed generation
- 12 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 982 lb CO2/MWh
- Water withdrawals
- 232 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 23,618 employed in construction within ~120 km (36 of 43 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Williamson
The sections below set out what public data shows about siting a large electrical load in Williamson, Illinois. At 345 kV, Williamson carries high-voltage transmission at its strongest mapped point. Williamson contains 59 mapped substations, a dense footprint that spreads interconnection options across many points.
Wholesale activity over Williamson clears through the MISO market (Midcontinent Independent System Operator), whose footprint sets how interconnection requests and capacity are handled. Williamson carries the state industrial average retail rate of 10.1 cents per kWh from EIA-861, applied statewide. For Williamson, the per-utility spread is 2 of 4 serving utilities: 1.6 to 10.4¢/kWh, which qualifies but never replaces the state average.
Williamson carries 3 projects in the interconnection queue, totalling 640 MW of requested capacity. In Williamson, 12 MW is filed as planned or under construction in the federal EIA-860M inventory. In eGRID, the balancing authority over Williamson shows 981.982 lb CO2 per MWh.
For Williamson, the USGS 2015 compilation records 232.48 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Williamson sits within commuting range of roughly 23,618 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.
Every figure for Williamson here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Williamson, Illinois settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Williamson, Illinois requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Williamson, Illinois are logged directly below, so each figure on this page can be traced back to its public dataset.