Orange, IN: data center power outlook

Orange, Indiana is served through the MISO market (Midcontinent Independent System Operator), and the figures below describe the public grid around a prospective data center site there. Orange carries 21 mapped substations within its boundary, and the highest reachable grid access is 345 kV. Service in Orange spans 7 utilities, with DAVIESS MARTIN COUNTY R E M C, DUBOIS RURAL ELECTRIC COOP INC, DUKE ENERGY INDIANA, LLC among those mapped.

Grid position at a glance

Serving utilities
DAVIESS MARTIN COUNTY R E M C, DUBOIS RURAL ELECTRIC COOP INC, DUKE ENERGY INDIANA, LLC, HARRISON COUNTY RURAL E M C, JACKSON COUNTY RURAL E M C - (IN), ORANGE COUNTY RURAL E M C, TOWN OF PAOLI
ISO / market
MISO (Midcontinent Independent System Operator)
Highest grid access
345 kV
Substations in county
21
Industrial retail rate
8.9¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
5 of 7 serving utilities: 7.9 to 11.4¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
2 projects, 400 MW
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
982 lb CO2/MWh
Water withdrawals
1.3 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
69,671 employed in construction within ~120 km (44 of 45 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Orange

The material below frames Orange, Indiana for a prospective large load, drawing only on public sources. Grid access in Orange extends to 345 kV, a high-voltage line class. The mapped layer packs 21 substations into Orange, a dense spread of options.

Interconnection over Orange runs through the MISO market (Midcontinent Independent System Operator) and its rules. For Orange, the rate shown is the state industrial average of 8.9 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Orange that report an industrial rate span 5 of 7 serving utilities: 7.9 to 11.4¢/kWh, shown as context and never as the county rate.

The queue feeds show 2 projects for Orange, totalling 400 MW of requested capacity. Nothing is on file for Orange, Indiana in EIA-860M as planned or under construction, which counts as a measured zero. Orange sits under a balancing authority that eGRID puts at 981.982 lb CO2 per MWh.

Orange withdrew 1.29 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 69,671 people are employed in construction within a 120 km commute of Orange (BLS QCEW), which frames staffing distance rather than free labour.

For Orange, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Orange, Indiana describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Orange, Indiana, a specific address needs its own interconnection study, which this page does not attempt. The figures for Orange, Indiana refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.