Power by county
Wright, IA: data center power outlook
The grid around Wright, Iowa is summarized here from public data, starting from the county's position in the SPP market (Southwest Power Pool). Inside Wright the mapped layer shows 13 mapped substations, with grid access reaching 161 kV at its strongest point. Retail service across Wright is split among 9 utilities, among them BOONE VALLEY ELECTRIC COOP, CASS ELECTRIC COOP, CITY OF WOOLSTOCK - (IA).
Grid position at a glance
- Serving utilities
- BOONE VALLEY ELECTRIC COOP, CASS ELECTRIC COOP, CITY OF WOOLSTOCK - (IA), FEDERATED RURAL ELECTRIC ASSN, FRANKLIN RURAL ELECTRIC COOP - (IA), INTERSTATE POWER AND LIGHT CO, MIDAMERICAN ENERGY CO, MIDLAND POWER COOP, PRAIRIE ENERGY COOP
- ISO / market
- SPP (Southwest Power Pool)
- Highest grid access
- 161 kV
- Substations in county
- 13
- Industrial retail rate
- 7.2¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 5 of 9 serving utilities: 6.0 to 15.3¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- 1 projects, 38 MW
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 982 lb CO2/MWh
- Water withdrawals
- 6.8 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 36,630 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Wright
Read on for the public power picture of Wright in Iowa, assembled for data center siting. Transmission-class access reaches 161 kV in Wright at its strongest mapped point. Wright contains 13 mapped substations, a moderate footprint spread across the service area.
Wholesale activity over Wright clears through the SPP market (Southwest Power Pool), whose footprint sets how interconnection requests and capacity are handled. Wright carries the state industrial average retail rate of 7.2 cents per kWh from EIA-861, applied statewide. For Wright, the per-utility spread is 5 of 9 serving utilities: 6.0 to 15.3¢/kWh, which qualifies but never replaces the state average.
Wright carries 1 project in the interconnection queue, totalling 38 MW of requested capacity. No generation is filed as planned or under construction in Wright, Iowa in the federal EIA-860M inventory, a measured zero rather than missing data. In eGRID, the balancing authority over Wright shows 981.982 lb CO2 per MWh.
For Wright, the USGS 2015 compilation records 6.84 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Wright sits within commuting range of roughly 36,630 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.
Every figure for Wright here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Wright, Iowa settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Wright, Iowa requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Wright, Iowa are logged directly below, so each figure on this page can be traced back to its public dataset.