Ellis, KS: data center power outlook

Ellis, Kansas is served through the SPP market (Southwest Power Pool), and the figures below describe the public grid around a prospective data center site there. Ellis carries 21 mapped substations within its boundary, and the highest reachable grid access is 345 kV. Service in Ellis spans 5 utilities, with LANE-SCOTT ELECTRIC COOP, INC, MIDWEST ENERGY INC, PRAIRIE LAND ELECTRIC COOP INC among those mapped.

Grid position at a glance

Serving utilities
LANE-SCOTT ELECTRIC COOP, INC, MIDWEST ENERGY INC, PRAIRIE LAND ELECTRIC COOP INC, ROLLING HILLS ELECTRIC COOP, WESTERN COOP ELECTRIC ASSN INC
ISO / market
SPP (Southwest Power Pool)
Highest grid access
345 kV
Substations in county
21
Industrial retail rate
8.0¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 of 5 serving utilities: 7.6 to 13.3¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
872 lb CO2/MWh
Water withdrawals
4.6 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
2,414 employed in construction within ~120 km (17 of 22 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Ellis

What follows is a screening-grade read of Ellis, Kansas, built only from named public datasets. Grid access in Ellis extends to 345 kV, a high-voltage line class. The mapped layer packs 21 substations into Ellis, a dense spread of options.

Interconnection over Ellis runs through the SPP market (Southwest Power Pool) and its rules. For Ellis, the rate shown is the state industrial average of 8.0 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Ellis that report an industrial rate span 3 of 5 serving utilities: 7.6 to 13.3¢/kWh, shown as context and never as the county rate.

No interconnection-queue project is on record for Ellis, Kansas in the covered feeds, which reflects either genuine quiet or a queue not yet ingested. EIA-860M lists nothing planned or under construction for Ellis, Kansas, which is a national filing and so a real zero. Ellis sits under a balancing authority that eGRID puts at 871.526 lb CO2 per MWh.

Ellis withdrew 4.62 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 2,414 people are employed in construction within a 120 km commute of Ellis (BLS QCEW), which frames staffing distance rather than free labour.

For Ellis, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Ellis, Kansas describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Ellis, Kansas, a specific address needs its own interconnection study, which this page does not attempt. The figures for Ellis, Kansas refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.