Power by county
Logan, KS: data center power outlook
Logan sits in the SPP market (Southwest Power Pool); what follows is the screening-grade grid picture for Logan, Kansas, drawn from public datasets. Counting from the mapped infrastructure, Logan holds 5 mapped substations and reaches 345 kV. Logan is covered by 4 retail service territories, including LANE-SCOTT ELECTRIC COOP, INC, MIDWEST ENERGY INC, WESTERN COOP ELECTRIC ASSN INC.
Grid position at a glance
- Serving utilities
- LANE-SCOTT ELECTRIC COOP, INC, MIDWEST ENERGY INC, WESTERN COOP ELECTRIC ASSN INC, WHEATLAND ELECTRIC COOP, INC
- ISO / market
- SPP (Southwest Power Pool)
- Highest grid access
- 345 kV
- Substations in county
- 5
- Industrial retail rate
- 8.0¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 3 of 4 serving utilities: 7.8 to 13.3¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 872 lb CO2/MWh
- Water withdrawals
- 8.0 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 1,511 employed in construction within ~120 km (11 of 19 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Logan
Everything here about Logan, Kansas comes from public federal and state records, with the gaps left visible. Logan reaches 345 kV, a high-voltage transmission class, at its strongest mapped point of grid access. Only 5 substations is mapped in Logan, Kansas, keeping interconnection points few.
Logan falls inside the SPP market (Southwest Power Pool), which governs how its interconnection requests and capacity move. The rate for Logan is the 8.0 cents per kWh state industrial average (EIA-861), the same figure the map colours by. Across Logan, reported per-utility industrial rates cover 3 of 4 serving utilities: 7.8 to 13.3¢/kWh, offered only as context beneath the state figure.
No interconnection-queue project is on record for Logan, Kansas in the covered feeds, which reflects either genuine quiet or a queue not yet ingested. EIA-860M lists nothing planned or under construction for Logan, Kansas, which is a national filing and so a real zero. The balancing authority covering Logan carries a grid carbon intensity of 871.526 lb CO2 per MWh in eGRID.
Reported freshwater withdrawals for all uses in Logan are 7.96 million gallons per day in the USGS 2015 compilation, existing demand rather than water free for a new load. Around Logan, some 1,511 people work in construction within about a 120 km commute (BLS QCEW), a measure of reach, not of available crews.
These numbers for Logan are screening-grade context for the whole county, drawn from public data with the gaps left visible. Read the figures for Logan, Kansas together rather than one at a time: grid access matters less without substations near it, and a quiet queue reads differently inside an organized market than outside one. The next step for Logan, Kansas is an address-level interconnection study; the county figures here only narrow where to look. For Logan, Kansas, the source log below records where each figure comes from and when it was pulled, keeping the provenance visible.