Power by county
Saline, KS: data center power outlook
Saline, Kansas is served through the SPP market (Southwest Power Pool), and the figures below describe the public grid around a prospective data center site there. Saline carries 15 mapped substations within its boundary, and the highest reachable grid access is 345 kV. Service in Saline spans 8 utilities, with ARK VALLEY ELEC COOP ASSN, INC, BLUESTEM ELECTRIC COOP INC, DS&O ELECTRIC COOPERATIVE, INC. among those mapped.
Grid position at a glance
- Serving utilities
- ARK VALLEY ELEC COOP ASSN, INC, BLUESTEM ELECTRIC COOP INC, DS&O ELECTRIC COOPERATIVE, INC., EVERGY KANSAS CENTRAL, INC, EVERGY KANSAS SOUTH, INC, FLINT HILLS RURAL E C A, INC, ROLLING HILLS ELECTRIC COOP, WESTERN COOP ELECTRIC ASSN INC
- ISO / market
- SPP (Southwest Power Pool)
- Highest grid access
- 345 kV
- Substations in county
- 15
- Industrial retail rate
- 8.0¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 3 of 8 serving utilities: 7.6 to 13.3¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 872 lb CO2/MWh
- Water withdrawals
- 10 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 8,421 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Saline
The material below frames Saline, Kansas for a prospective large load, drawing only on public sources. Grid access in Saline extends to 345 kV, a high-voltage line class. The mapped layer places 15 substations across Saline, a moderate density.
Interconnection over Saline runs through the SPP market (Southwest Power Pool) and its rules. For Saline, the rate shown is the state industrial average of 8.0 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Saline that report an industrial rate span 3 of 8 serving utilities: 7.6 to 13.3¢/kWh, shown as context and never as the county rate.
No interconnection-queue project is on record for Saline, Kansas in the covered feeds, which reflects either genuine quiet or a queue not yet ingested. Nothing is on file for Saline, Kansas in EIA-860M as planned or under construction, which counts as a measured zero. Saline sits under a balancing authority that eGRID puts at 871.526 lb CO2 per MWh.
Saline withdrew 10.04 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 8,421 people are employed in construction within a 120 km commute of Saline (BLS QCEW), which frames staffing distance rather than free labour.
For Saline, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Saline, Kansas describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Saline, Kansas, a specific address needs its own interconnection study, which this page does not attempt. The figures for Saline, Kansas refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.