Carroll, Kentucky is served through the PJM market (PJM Interconnection), and the figures below describe the public grid around a prospective data center site there. Carroll carries 15 mapped substations within its boundary, and the highest reachable grid access is 765 kV. Service in Carroll spans 6 utilities, with DUKE ENERGY INDIANA, LLC, EAST KENTUCKY POWER COOP, INC, KENTUCKY UTILITIES CO among those mapped.
Grid position at a glance
- Serving utilities
- DUKE ENERGY INDIANA, LLC, EAST KENTUCKY POWER COOP, INC, KENTUCKY UTILITIES CO, OWEN ELECTRIC COOP INC, SHELBY ENERGY CO-OP, INC, SOUTHEASTERN INDIANA R E M C
- ISO / market
- PJM (PJM Interconnection)
- Highest grid access
- 765 kV
- Substations in county
- 15
- Industrial retail rate
- 7.0¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 3 of 6 serving utilities: 6.1 to 8.4¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- No eGRID rate published for this balancing authority
- Water withdrawals
- 42 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 110,149 employed in construction within ~120 km (49 of 57 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Carroll
What follows is a screening-grade read of Carroll, Kentucky, built only from named public datasets. Grid access in Carroll extends to 765 kV, the extra-high-voltage class. The mapped layer places 15 substations across Carroll, a moderate density.
Interconnection over Carroll runs through the PJM market (PJM Interconnection) and its rules. For Carroll, the rate shown is the state industrial average of 7.0 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Carroll that report an industrial rate span 3 of 6 serving utilities: 6.1 to 8.4¢/kWh, shown as context and never as the county rate.
The covered queue feeds list nothing for Carroll, Kentucky, which may be quiet or simply uningested. Carroll, Kentucky has no EIA-860M generation on file, which reads as zero rather than as a gap. For Carroll, Kentucky, eGRID rates no output for the covering balancing authority, and the carbon field stays empty.
Carroll withdrew 41.66 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 110,149 people are employed in construction within a 120 km commute of Carroll (BLS QCEW), which frames staffing distance rather than free labour.
For Carroll, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Carroll, Kentucky describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Carroll, Kentucky, a specific address needs its own interconnection study, which this page does not attempt. The figures for Carroll, Kentucky refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.