Power by county
Kenton, KY: data center power outlook
Kenton, Kentucky is served through the PJM market (PJM Interconnection), and the figures below describe the public grid around a prospective data center site there. Kenton carries 36 mapped substations within its boundary, and the highest reachable grid access is 345 kV. Service in Kenton spans 4 utilities, with DUKE ENERGY KENTUCKY, DUKE ENERGY OHIO INC, EAST KENTUCKY POWER COOP, INC among those mapped.
Grid position at a glance
- Serving utilities
- DUKE ENERGY KENTUCKY, DUKE ENERGY OHIO INC, EAST KENTUCKY POWER COOP, INC, OWEN ELECTRIC COOP INC
- ISO / market
- PJM (PJM Interconnection)
- Highest grid access
- 345 kV
- Substations in county
- 36
- Industrial retail rate
- 7.0¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 2 of 4 serving utilities: 6.1 to 9.8¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 716 lb CO2/MWh
- Water withdrawals
- 0.6 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 88,450 employed in construction within ~120 km (45 of 54 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Kenton
The material below frames Kenton, Kentucky for a prospective large load, drawing only on public sources. Grid access in Kenton extends to 345 kV, a high-voltage line class. The mapped layer packs 36 substations into Kenton, a dense spread of options.
Interconnection over Kenton runs through the PJM market (PJM Interconnection) and its rules. For Kenton, the rate shown is the state industrial average of 7.0 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Kenton that report an industrial rate span 2 of 4 serving utilities: 6.1 to 9.8¢/kWh, shown as context and never as the county rate.
Across the covered feeds, Kenton, Kentucky carries no interconnection-queue project, from either real quiet or a feed not yet loaded. Nothing is on file for Kenton, Kentucky in EIA-860M as planned or under construction, which counts as a measured zero. Kenton sits under a balancing authority that eGRID puts at 716.09 lb CO2 per MWh.
Kenton withdrew 0.6 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 88,450 people are employed in construction within a 120 km commute of Kenton (BLS QCEW), which frames staffing distance rather than free labour.
For Kenton, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Kenton, Kentucky describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Kenton, Kentucky, a specific address needs its own interconnection study, which this page does not attempt. The figures for Kenton, Kentucky refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.