De Soto, Louisiana is served through the SPP market (Southwest Power Pool), and the figures below describe the public grid around a prospective data center site there. De Soto carries 15 mapped substations within its boundary, and the highest reachable grid access is 345 kV. Service in De Soto spans 7 utilities, with CLECO POWER LLC, DEEP EAST TEXAS ELEC COOP INC, ENTERGY LOUISIANA LLC among those mapped.

Grid position at a glance

Serving utilities
CLECO POWER LLC, DEEP EAST TEXAS ELEC COOP INC, ENTERGY LOUISIANA LLC, PANOLA-HARRISON ELEC COOP, INC, RUSK COUNTY ELECTRIC COOP, INC, SOUTHWEST LOUISIANA E M C, SOUTHWESTERN ELECTRIC POWER CO
ISO / market
SPP (Southwest Power Pool)
Highest grid access
345 kV
Substations in county
15
Industrial retail rate
6.2¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
5 of 7 serving utilities: 5.2 to 9.6¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
5 projects, 1,095 MW
Proposed generation
240 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
982 lb CO2/MWh
Water withdrawals
28 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
21,842 employed in construction within ~120 km (18 of 20 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in De Soto

The material below frames De Soto, Louisiana for a prospective large load, drawing only on public sources. Grid access in De Soto extends to 345 kV, a high-voltage line class. The mapped layer places 15 substations across De Soto, a moderate density.

Interconnection over De Soto runs through the SPP market (Southwest Power Pool) and its rules. For De Soto, the rate shown is the state industrial average of 6.2 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving De Soto that report an industrial rate span 5 of 7 serving utilities: 5.2 to 9.6¢/kWh, shown as context and never as the county rate.

The queue feeds show 5 projects for De Soto, totalling 1,095 MW of requested capacity. EIA-860M records 240 MW planned or under construction for De Soto. De Soto sits under a balancing authority that eGRID puts at 981.982 lb CO2 per MWh.

De Soto withdrew 28.11 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 21,842 people are employed in construction within a 120 km commute of De Soto (BLS QCEW), which frames staffing distance rather than free labour.

For De Soto, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for De Soto, Louisiana describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in De Soto, Louisiana, a specific address needs its own interconnection study, which this page does not attempt. The figures for De Soto, Louisiana refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.

Sources