Power by county
Knox, ME: data center power outlook
The grid around Knox, Maine is summarized here from public data, starting from the county's position in the ISONE market (ISO New England). Inside Knox the mapped layer shows 6 mapped substations, with grid access reaching 345 kV at its strongest point. Retail service across Knox is split among 4 utilities, among them CENTRAL MAINE POWER CO, FOX ISLANDS ELECTRIC COOP, INC, MATINICUS PLANTATION ELEC CO.
Grid position at a glance
- Serving utilities
- CENTRAL MAINE POWER CO, FOX ISLANDS ELECTRIC COOP, INC, MATINICUS PLANTATION ELEC CO, VERSANT POWER
- ISO / market
- ISONE (ISO New England)
- Highest grid access
- 345 kV
- Substations in county
- 6
- Industrial retail rate
- 15.5¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 2 of 4 serving utilities: 5.0 to 8.2¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- 75 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 541 lb CO2/MWh
- Water withdrawals
- 4.5 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 21,895 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Knox
Read on for the public power picture of Knox in Maine, assembled for data center siting. At 345 kV, Knox carries high-voltage transmission at its strongest mapped point. Knox contains 6 mapped substations, a moderate footprint spread across the service area.
Wholesale activity over Knox clears through the ISONE market (ISO New England), whose footprint sets how interconnection requests and capacity are handled. Knox carries the state industrial average retail rate of 15.5 cents per kWh from EIA-861, applied statewide. For Knox, the per-utility spread is 2 of 4 serving utilities: 5.0 to 8.2¢/kWh, which qualifies but never replaces the state average.
Knox, Maine has nothing in the interconnection queue across the feeds covered here, quiet or uningested. In Knox, 74.5 MW is filed as planned or under construction in the federal EIA-860M inventory. In eGRID, the balancing authority over Knox shows 541.365 lb CO2 per MWh.
For Knox, the USGS 2015 compilation records 4.45 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Knox sits within commuting range of roughly 21,895 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.
Every figure for Knox here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Knox, Maine settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Knox, Maine requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Knox, Maine are logged directly below, so each figure on this page can be traced back to its public dataset.