Barry, MI: data center power outlook
Barry sits in the MISO market (Midcontinent Independent System Operator); what follows is the screening-grade grid picture for Barry, Michigan, drawn from public datasets. Counting from the mapped infrastructure, Barry holds 8 mapped substations and reaches 345 kV. Barry is covered by 6 retail service territories, including CONSUMERS ENERGY CO, DTE ELECTRIC COMPANY, GREAT LAKES ENERGY COOP.
Grid position at a glance
- Serving utilities
- CONSUMERS ENERGY CO, DTE ELECTRIC COMPANY, GREAT LAKES ENERGY COOP, MIDWEST ENERGY COOPERATIVE, TRI-COUNTY ELECTRIC COOP (MI), WOLVERINE POWER SUPPLY COOP
- ISO / market
- MISO (Midcontinent Independent System Operator)
- Highest grid access
- 345 kV
- Substations in county
- 8
- Industrial retail rate
- 8.6¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 4 of 6 serving utilities: 6.6 to 10.5¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- 1 projects, 150 MW
- Proposed generation
- 2 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 982 lb CO2/MWh
- Water withdrawals
- 9.8 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 75,399 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Barry
Below, Barry in Michigan is described from public data as a starting point for siting diligence. Barry reaches 345 kV, a high-voltage transmission class, at its strongest mapped point of grid access. With 8 substations mapped, Barry has a moderate spread of interconnection points.
Barry falls inside the MISO market (Midcontinent Independent System Operator), which governs how its interconnection requests and capacity move. The rate for Barry is the 8.6 cents per kWh state industrial average (EIA-861), the same figure the map colours by. Across Barry, reported per-utility industrial rates cover 4 of 6 serving utilities: 6.6 to 10.5¢/kWh, offered only as context beneath the state figure.
Barry has 1 interconnection-queue project on record, totalling 150 MW of requested capacity. Barry has 1.6 MW of planned or under-construction generation on file in EIA-860M. The balancing authority covering Barry carries a grid carbon intensity of 981.982 lb CO2 per MWh in eGRID.
Reported freshwater withdrawals for all uses in Barry are 9.81 million gallons per day in the USGS 2015 compilation, existing demand rather than water free for a new load. Around Barry, some 75,399 people work in construction within about a 120 km commute (BLS QCEW), a measure of reach, not of available crews.
These numbers for Barry are screening-grade context for the whole county, drawn from public data with the gaps left visible. Read the figures for Barry, Michigan together rather than one at a time: grid access matters less without substations near it, and a quiet queue reads differently inside an organized market than outside one. The next step for Barry, Michigan is an address-level interconnection study; the county figures here only narrow where to look. For Barry, Michigan, the source log below records where each figure comes from and when it was pulled, keeping the provenance visible.