Power by county
Hennepin, MN: data center power outlook
The grid around Hennepin, Minnesota is summarized here from public data, starting from the county's position in the MISO market (Midcontinent Independent System Operator). Inside Hennepin the mapped layer shows 73 mapped substations, with grid access reaching 345 kV at its strongest point. Retail service across Hennepin is split among 8 utilities, among them CITY OF ANOKA, CITY OF ELK RIVER, CITY OF ST PAUL - (NE).
Grid position at a glance
- Serving utilities
- CITY OF ANOKA, CITY OF ELK RIVER, CITY OF ST PAUL - (NE), CONNEXUS ENERGY, MINNESOTA VALLEY ELECTRIC COOP, NORTHERN STATES POWER CO - MINNESOTA, SHAKOPEE PUBLIC UTILITIES COMM, WRIGHT-HENNEPIN COOP ELEC ASSN
- ISO / market
- MISO (Midcontinent Independent System Operator)
- Highest grid access
- 345 kV
- Substations in county
- 73
- Industrial retail rate
- 9.3¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 6 of 8 serving utilities: 7.9 to 12.4¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- 1 projects, 55 MW
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 982 lb CO2/MWh
- Water withdrawals
- 189 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 112,940 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Hennepin
Read on for the public power picture of Hennepin in Minnesota, assembled for data center siting. At 345 kV, Hennepin carries high-voltage transmission at its strongest mapped point. Hennepin contains 73 mapped substations, a dense footprint that spreads interconnection options across many points.
Wholesale activity over Hennepin clears through the MISO market (Midcontinent Independent System Operator), whose footprint sets how interconnection requests and capacity are handled. Hennepin carries the state industrial average retail rate of 9.3 cents per kWh from EIA-861, applied statewide. For Hennepin, the per-utility spread is 6 of 8 serving utilities: 7.9 to 12.4¢/kWh, which qualifies but never replaces the state average.
Hennepin carries 1 project in the interconnection queue, totalling 55 MW of requested capacity. No generation is filed as planned or under construction in Hennepin, Minnesota in the federal EIA-860M inventory, a measured zero rather than missing data. In eGRID, the balancing authority over Hennepin shows 981.982 lb CO2 per MWh.
For Hennepin, the USGS 2015 compilation records 189.35 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Hennepin sits within commuting range of roughly 112,940 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.
Every figure for Hennepin here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Hennepin, Minnesota settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Hennepin, Minnesota requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Hennepin, Minnesota are logged directly below, so each figure on this page can be traced back to its public dataset.