Power by county

Hinds, MS: data center power outlook

The grid around Hinds, Mississippi is summarized here from public data, starting from the county's position in the MISO market (Midcontinent Independent System Operator). Inside Hinds the mapped layer shows 44 mapped substations, with grid access reaching 500 kV at its strongest point. Retail service across Hinds is split among 4 utilities, among them ENTERGY MISSISSIPPI LLC, SOUTHERN PINE ELECTRIC COOPERATIVE, SOUTHWEST MISSISSIPPI E P A.

Grid position at a glance

Serving utilities
ENTERGY MISSISSIPPI LLC, SOUTHERN PINE ELECTRIC COOPERATIVE, SOUTHWEST MISSISSIPPI E P A, YAZOO VALLEY ELEC POWER ASSN
ISO / market
MISO (Midcontinent Independent System Operator)
Highest grid access
500 kV
Substations in county
44
Industrial retail rate
7.4¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
4 serving utilities: 6.9 to 9.6¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
16 projects, 3,831 MW
Proposed generation
150 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
982 lb CO2/MWh
Water withdrawals
58 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
15,785 employed in construction within ~120 km (22 of 27 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Hinds

The sections below set out what public data shows about siting a large electrical load in Hinds, Mississippi. At 500 kV, Hinds carries high-voltage transmission at its strongest mapped point. Hinds contains 44 mapped substations, a dense footprint that spreads interconnection options across many points.

Wholesale activity over Hinds clears through the MISO market (Midcontinent Independent System Operator), whose footprint sets how interconnection requests and capacity are handled. Hinds carries the state industrial average retail rate of 7.4 cents per kWh from EIA-861, applied statewide. For Hinds, the per-utility spread is 4 serving utilities: 6.9 to 9.6¢/kWh, which qualifies but never replaces the state average.

Hinds carries 16 projects in the interconnection queue, totalling 3,831 MW of requested capacity. In Hinds, 150 MW is filed as planned or under construction in the federal EIA-860M inventory. In eGRID, the balancing authority over Hinds shows 981.982 lb CO2 per MWh.

For Hinds, the USGS 2015 compilation records 57.5 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Hinds sits within commuting range of roughly 15,785 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Hinds here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Hinds, Mississippi settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Hinds, Mississippi requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Hinds, Mississippi are logged directly below, so each figure on this page can be traced back to its public dataset.

Sources