Clinton, MO: data center power outlook

Clinton, Missouri is served through the MISO market (Midcontinent Independent System Operator), and the figures below describe the public grid around a prospective data center site there. Clinton carries 15 mapped substations within its boundary, and the highest reachable grid access is 161 kV. Service in Clinton spans 6 utilities, with CITY OF CAMERON, EVERGY MISSOURI WEST, FARMERS ELECTRIC COOP, INC - (MO) among those mapped.

Grid position at a glance

Serving utilities
CITY OF CAMERON, EVERGY MISSOURI WEST, FARMERS ELECTRIC COOP, INC - (MO), PLATTE-CLAY ELECTRIC COOP, INC, UNION ELECTRIC CO - (MO), UNITED ELECTRIC COOP, INC - (MO)
ISO / market
MISO (Midcontinent Independent System Operator)
Highest grid access
161 kV
Substations in county
15
Industrial retail rate
8.4¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
4 of 6 serving utilities: 6.9 to 13.4¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
419 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
1,285 lb CO2/MWh
Water withdrawals
1.0 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
67,959 employed in construction within ~120 km (31 of 32 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Clinton

What follows is a screening-grade read of Clinton, Missouri, built only from named public datasets. At 161 kV, Clinton sits in the transmission class that a large load would look to. The mapped layer places 15 substations across Clinton, a moderate density.

Interconnection over Clinton runs through the MISO market (Midcontinent Independent System Operator) and its rules. For Clinton, the rate shown is the state industrial average of 8.4 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Clinton that report an industrial rate span 4 of 6 serving utilities: 6.9 to 13.4¢/kWh, shown as context and never as the county rate.

Across the covered feeds, Clinton, Missouri carries no interconnection-queue project, from either real quiet or a feed not yet loaded. EIA-860M records 419 MW planned or under construction for Clinton. Clinton sits under a balancing authority that eGRID puts at 1,285.192 lb CO2 per MWh.

Clinton withdrew 1.02 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 67,959 people are employed in construction within a 120 km commute of Clinton (BLS QCEW), which frames staffing distance rather than free labour.

For Clinton, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Clinton, Missouri describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Clinton, Missouri, a specific address needs its own interconnection study, which this page does not attempt. The figures for Clinton, Missouri refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.