Macon, MO: data center power outlook

The grid around Macon, Missouri is summarized here from public data, starting from the county's position in the SPP market (Southwest Power Pool). Inside Macon the mapped layer shows 20 mapped substations, with grid access reaching 161 kV at its strongest point. Retail service across Macon is split among 7 utilities, among them CITY OF LA PLATA - (MO), CITY OF MACON - (MO), EVERGY MISSOURI WEST.

Grid position at a glance

Serving utilities
CITY OF LA PLATA - (MO), CITY OF MACON - (MO), EVERGY MISSOURI WEST, MACON ELECTRIC COOP, NORTH CENTRAL MO ELEC COOP INC, TRI-COUNTY ELECTRIC COOP ASSN (MO), UNION ELECTRIC CO - (MO)
ISO / market
SPP (Southwest Power Pool)
Highest grid access
161 kV
Substations in county
20
Industrial retail rate
8.4¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 of 7 serving utilities: 6.9 to 7.6¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
4 projects, 1,008 MW
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
1,285 lb CO2/MWh
Water withdrawals
3.6 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
7,716 employed in construction within ~120 km (24 of 28 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Macon

Read on for the public power picture of Macon in Missouri, assembled for data center siting. Transmission-class access reaches 161 kV in Macon at its strongest mapped point. Macon contains 20 mapped substations, a moderate footprint spread across the service area.

Wholesale activity over Macon clears through the SPP market (Southwest Power Pool), whose footprint sets how interconnection requests and capacity are handled. Macon carries the state industrial average retail rate of 8.4 cents per kWh from EIA-861, applied statewide. For Macon, the per-utility spread is 3 of 7 serving utilities: 6.9 to 7.6¢/kWh, which qualifies but never replaces the state average.

Macon carries 4 projects in the interconnection queue, totalling 1,008.43 MW of requested capacity. The federal EIA-860M inventory files no planned or under-construction generation in Macon, Missouri, a real zero rather than a gap. In eGRID, the balancing authority over Macon shows 1,285.192 lb CO2 per MWh.

For Macon, the USGS 2015 compilation records 3.64 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Macon sits within commuting range of roughly 7,716 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Macon here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Macon, Missouri settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Macon, Missouri requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Macon, Missouri are logged directly below, so each figure on this page can be traced back to its public dataset.