Maries, MO: data center power outlook

The grid around Maries, Missouri is summarized here from public data, starting from the county's position in an area outside an organized wholesale market. Inside Maries the mapped layer shows 7 mapped substations, with grid access reaching 345 kV at its strongest point. Retail service across Maries is split among 4 utilities, among them GASCOSAGE ELECTRIC COOP, INTERCOUNTY ELECTRIC COOP ASSN, THREE RIVERS ELECTRIC COOP.

Grid position at a glance

Serving utilities
GASCOSAGE ELECTRIC COOP, INTERCOUNTY ELECTRIC COOP ASSN, THREE RIVERS ELECTRIC COOP, UNION ELECTRIC CO - (MO)
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
345 kV
Substations in county
7
Industrial retail rate
8.4¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
4 serving utilities: 6.9 to 9.7¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
3 projects, 540 MW
Proposed generation
400 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
1,285 lb CO2/MWh
Water withdrawals
1.6 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
23,120 employed in construction within ~120 km (24 of 25 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Maries

The sections below set out what public data shows about siting a large electrical load in Maries, Missouri. At 345 kV, Maries carries high-voltage transmission at its strongest mapped point. Maries contains 7 mapped substations, a moderate footprint spread across the service area.

Maries, Missouri lies outside an organized wholesale market, so generation and transmission are arranged bilaterally and through the local utility rather than a central market operator. Maries carries the state industrial average retail rate of 8.4 cents per kWh from EIA-861, applied statewide. For Maries, the per-utility spread is 4 serving utilities: 6.9 to 9.7¢/kWh, which qualifies but never replaces the state average.

Maries carries 3 projects in the interconnection queue, totalling 540 MW of requested capacity. In Maries, 400 MW is filed as planned or under construction in the federal EIA-860M inventory. In eGRID, the balancing authority over Maries shows 1,285.192 lb CO2 per MWh.

For Maries, the USGS 2015 compilation records 1.64 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Maries sits within commuting range of roughly 23,120 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Maries here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Maries, Missouri settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Maries, Missouri requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Maries, Missouri are logged directly below, so each figure on this page can be traced back to its public dataset.