Douglas, NE: data center power outlook

Douglas sits in the SPP market (Southwest Power Pool); what follows is the screening-grade grid picture for Douglas, Nebraska, drawn from public datasets. Counting from the mapped infrastructure, Douglas holds 43 mapped substations and reaches 345 kV. Douglas is covered by 2 retail service territories, including MIDAMERICAN ENERGY CO, OMAHA PUBLIC POWER DISTRICT.

Grid position at a glance

Serving utilities
MIDAMERICAN ENERGY CO, OMAHA PUBLIC POWER DISTRICT
ISO / market
SPP (Southwest Power Pool)
Highest grid access
345 kV
Substations in county
43
Industrial retail rate
8.0¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
1 of 2 serving utilities: 7.0¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
872 lb CO2/MWh
Water withdrawals
614 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
49,380 employed in construction within ~120 km (28 of 32 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Douglas

Everything here about Douglas, Nebraska comes from public federal and state records, with the gaps left visible. Douglas reaches 345 kV, a high-voltage transmission class, at its strongest mapped point of grid access. With 43 substations mapped, Douglas offers interconnection points across many locations.

Douglas falls inside the SPP market (Southwest Power Pool), which governs how its interconnection requests and capacity move. The rate for Douglas is the 8.0 cents per kWh state industrial average (EIA-861), the same figure the map colours by. Across Douglas, reported per-utility industrial rates cover 1 of 2 serving utilities: 7.0¢/kWh, offered only as context beneath the state figure.

No interconnection-queue project is on record for Douglas, Nebraska in the covered feeds, which reflects either genuine quiet or a queue not yet ingested. EIA-860M lists nothing planned or under construction for Douglas, Nebraska, which is a national filing and so a real zero. The balancing authority covering Douglas carries a grid carbon intensity of 871.526 lb CO2 per MWh in eGRID.

Reported freshwater withdrawals for all uses in Douglas are 613.5 million gallons per day in the USGS 2015 compilation, existing demand rather than water free for a new load. Around Douglas, some 49,380 people work in construction within about a 120 km commute (BLS QCEW), a measure of reach, not of available crews.

These numbers for Douglas are screening-grade context for the whole county, drawn from public data with the gaps left visible. Read the figures for Douglas, Nebraska together rather than one at a time: grid access matters less without substations near it, and a quiet queue reads differently inside an organized market than outside one. The next step for Douglas, Nebraska is an address-level interconnection study; the county figures here only narrow where to look. For Douglas, Nebraska, the source log below records where each figure comes from and when it was pulled, keeping the provenance visible.