Power by county
Kimball, NE: data center power outlook
Kimball, Nebraska is served through an area outside an organized wholesale market, and the figures below describe the public grid around a prospective data center site there. Kimball carries 4 mapped substations within its boundary, and the highest reachable grid access is 345 kV. Service in Kimball spans 4 utilities, with BLACK HILLS POWER, INC., CITY OF KIMBALL - (NE), HIGH WEST ENERGY, INC among those mapped.
Grid position at a glance
- Serving utilities
- BLACK HILLS POWER, INC., CITY OF KIMBALL - (NE), HIGH WEST ENERGY, INC, WAPA-- WESTERN AREA POWER ADMINISTRATION
- ISO / market
- NON_ISO (Not in an organized wholesale market)
- Highest grid access
- 345 kV
- Substations in county
- 4
- Industrial retail rate
- 8.0¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 1 of 4 serving utilities: 11.7¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 872 lb CO2/MWh
- Water withdrawals
- 23 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 20,058 employed in construction within ~120 km (10 of 12 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Kimball
The material below frames Kimball, Nebraska for a prospective large load, drawing only on public sources. Grid access in Kimball extends to 345 kV, a high-voltage line class. The mapped footprint in Kimball, Nebraska is sparse, 4 substations, so options cluster at those points.
Because Kimball, Nebraska sits outside an organized market, capacity and interconnection are handled by the utility and bilateral deals, not a market operator. For Kimball, the rate shown is the state industrial average of 8.0 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Kimball that report an industrial rate span 1 of 4 serving utilities: 11.7¢/kWh, shown as context and never as the county rate.
The covered queue feeds list nothing for Kimball, Nebraska, which may be quiet or simply uningested. EIA-860M lists nothing planned or under construction for Kimball, Nebraska, which is a national filing and so a real zero. Kimball sits under a balancing authority that eGRID puts at 871.526 lb CO2 per MWh.
Kimball withdrew 22.5 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 20,058 people are employed in construction within a 120 km commute of Kimball (BLS QCEW), which frames staffing distance rather than free labour.
For Kimball, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Kimball, Nebraska describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Kimball, Nebraska, a specific address needs its own interconnection study, which this page does not attempt. The figures for Kimball, Nebraska refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.