Power by county

Gloucester, NJ: data center power outlook

For Gloucester, New Jersey, the public grid picture begins with its place in the PJM market (PJM Interconnection) and the infrastructure mapped inside the county. Grid access across Gloucester tops out at 500 kV, over a footprint of 20 mapped substations. In Gloucester, 4 utilities share the retail territory, among them ATLANTIC CITY ELECTRIC CO, DELMARVA POWER, PECO ENERGY CO.

Grid position at a glance

Serving utilities
ATLANTIC CITY ELECTRIC CO, DELMARVA POWER, PECO ENERGY CO, PUBLIC SERVICE ELEC & GAS CO
ISO / market
PJM (PJM Interconnection)
Highest grid access
500 kV
Substations in county
20
Industrial retail rate
13.9¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
2 of 4 serving utilities: 5.8 to 6.2¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
7 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
716 lb CO2/MWh
Water withdrawals
58 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
249,138 employed in construction within ~120 km (29 of 30 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Gloucester

This page gathers the public grid evidence for Gloucester, New Jersey that bears on a large new load. The highest mapped voltage in Gloucester is 500 kV, in the high-voltage transmission class. Gloucester carries 20 substations in the mapped layer, spread across the county.

For Gloucester, the PJM market (PJM Interconnection) is the operator that handles interconnection and capacity. The state industrial average retail rate is 13.9 cents per kWh, drawn from EIA-861 and applied to Gloucester at the state level rather than as a county rate. The serving utilities in Gloucester that publish a rate range 2 of 4 serving utilities: 5.8 to 6.2¢/kWh, a spread kept separate from the state average.

For Gloucester, New Jersey, no queued project appears in the feeds currently covered. Federal filings (EIA-860M) list 7 MW of generation as planned or under construction in Gloucester. Grid carbon intensity for Gloucester, via its balancing authority, is 716.09 lb CO2 per MWh in eGRID.

USGS 2015 puts freshwater withdrawals across Gloucester at 57.92 million gallons per day for all uses, a measure of use, not spare supply. Within roughly a 120 km commute of Gloucester, about 249,138 people are employed in construction (BLS QCEW), which speaks to how far crews for a multi-year build would travel, not to labour known to be free.

Read the Gloucester figures as screening-grade context: they describe the surrounding grid, not a specific parcel. The numbers for Gloucester, New Jersey qualify one another, so grid access, substation density, market membership, and rate are meant to be read as a set, not in isolation. Past this screening view, siting in Gloucester, New Jersey turns on a study of a particular address, something no county-level page can stand in for. Every number shown for Gloucester, New Jersey traces to a public source listed below, with its retrieval date, so the provenance is auditable rather than asserted.

Sources