Hudson, NJ: data center power outlook
The grid around Hudson, New Jersey is summarized here from public data, starting from the county's position in the PJM market (PJM Interconnection). Inside Hudson the mapped layer shows 28 mapped substations, with grid access reaching 345 kV at its strongest point. Retail service across Hudson is split among 2 utilities, among them CONSOLIDATED EDISON CO-NY INC, PUBLIC SERVICE ELEC & GAS CO.
Grid position at a glance
- Serving utilities
- CONSOLIDATED EDISON CO-NY INC, PUBLIC SERVICE ELEC & GAS CO
- ISO / market
- PJM (PJM Interconnection)
- Highest grid access
- 345 kV
- Substations in county
- 28
- Industrial retail rate
- 13.9¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 1 of 2 serving utilities: 6.2¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 716 lb CO2/MWh
- Water withdrawals
- 239 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 453,829 employed in construction within ~120 km (33 of 34 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Hudson
The sections below set out what public data shows about siting a large electrical load in Hudson, New Jersey. At 345 kV, Hudson carries high-voltage transmission at its strongest mapped point. Hudson contains 28 mapped substations, a dense footprint that spreads interconnection options across many points.
Wholesale activity over Hudson clears through the PJM market (PJM Interconnection), whose footprint sets how interconnection requests and capacity are handled. Hudson carries the state industrial average retail rate of 13.9 cents per kWh from EIA-861, applied statewide. For Hudson, the per-utility spread is 1 of 2 serving utilities: 6.2¢/kWh, which qualifies but never replaces the state average.
Hudson, New Jersey has nothing in the interconnection queue across the feeds covered here, quiet or uningested. The federal EIA-860M inventory files no planned or under-construction generation in Hudson, New Jersey, a real zero rather than a gap. In eGRID, the balancing authority over Hudson shows 716.09 lb CO2 per MWh.
For Hudson, the USGS 2015 compilation records 239.17 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Hudson sits within commuting range of roughly 453,829 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.
Every figure for Hudson here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Hudson, New Jersey settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Hudson, New Jersey requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Hudson, New Jersey are logged directly below, so each figure on this page can be traced back to its public dataset.