Cortland, NY: data center power outlook
Cortland, New York is served through the NYISO market (New York Independent System Operator), and the figures below describe the public grid around a prospective data center site there. Cortland carries 33 mapped substations within its boundary, and the highest reachable grid access is 345 kV. Service in Cortland spans 6 utilities, with DELAWARE COUNTY ELEC COOP INC, NEW YORK STATE ELEC & GAS CORP, NIAGARA MOHAWK POWER CORP. among those mapped.
Grid position at a glance
- Serving utilities
- DELAWARE COUNTY ELEC COOP INC, NEW YORK STATE ELEC & GAS CORP, NIAGARA MOHAWK POWER CORP., ONEIDA-MADISON ELEC COOP, INC, OTSEGO ELECTRIC COOP, INC, VILLAGE OF MARATHON - (NY)
- ISO / market
- NYISO (New York Independent System Operator)
- Highest grid access
- 345 kV
- Substations in county
- 33
- Industrial retail rate
- 9.6¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 2 of 6 serving utilities: 2.5 to 2.7¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- 1 projects, 90 MW
- Proposed generation
- 95 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 479 lb CO2/MWh
- Water withdrawals
- 5.7 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 33,836 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Cortland
What follows is a screening-grade read of Cortland, New York, built only from named public datasets. Grid access in Cortland extends to 345 kV, a high-voltage line class. The mapped layer packs 33 substations into Cortland, a dense spread of options.
Interconnection over Cortland runs through the NYISO market (New York Independent System Operator) and its rules. For Cortland, the rate shown is the state industrial average of 9.6 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Cortland that report an industrial rate span 2 of 6 serving utilities: 2.5 to 2.7¢/kWh, shown as context and never as the county rate.
The queue feeds show 1 project for Cortland, totalling 90 MW of requested capacity. EIA-860M records 95 MW planned or under construction for Cortland. Cortland sits under a balancing authority that eGRID puts at 479.212 lb CO2 per MWh.
Cortland withdrew 5.69 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 33,836 people are employed in construction within a 120 km commute of Cortland (BLS QCEW), which frames staffing distance rather than free labour.
For Cortland, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Cortland, New York describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Cortland, New York, a specific address needs its own interconnection study, which this page does not attempt. The figures for Cortland, New York refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.