Genesee, NY: data center power outlook

The grid around Genesee, New York is summarized here from public data, starting from the county's position in the NYISO market (New York Independent System Operator). Inside Genesee the mapped layer shows 28 mapped substations, with grid access reaching 345 kV at its strongest point. Retail service across Genesee is split among 4 utilities, among them NEW YORK STATE ELEC & GAS CORP, NIAGARA MOHAWK POWER CORP., VILLAGE OF BERGEN - (NY).

Grid position at a glance

Serving utilities
NEW YORK STATE ELEC & GAS CORP, NIAGARA MOHAWK POWER CORP., VILLAGE OF BERGEN - (NY), VILLAGE OF CHURCHVILLE - (NY)
ISO / market
NYISO (New York Independent System Operator)
Highest grid access
345 kV
Substations in county
28
Industrial retail rate
9.6¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
2 of 4 serving utilities: 2.5 to 2.7¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
5 projects, 1,206 MW
Proposed generation
861 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
479 lb CO2/MWh
Water withdrawals
18 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
50,092 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Genesee

The sections below set out what public data shows about siting a large electrical load in Genesee, New York. At 345 kV, Genesee carries high-voltage transmission at its strongest mapped point. Genesee contains 28 mapped substations, a dense footprint that spreads interconnection options across many points.

Wholesale activity over Genesee clears through the NYISO market (New York Independent System Operator), whose footprint sets how interconnection requests and capacity are handled. Genesee carries the state industrial average retail rate of 9.6 cents per kWh from EIA-861, applied statewide. For Genesee, the per-utility spread is 2 of 4 serving utilities: 2.5 to 2.7¢/kWh, which qualifies but never replaces the state average.

Genesee carries 5 projects in the interconnection queue, totalling 1,206 MW of requested capacity. In Genesee, 861 MW is filed as planned or under construction in the federal EIA-860M inventory. In eGRID, the balancing authority over Genesee shows 479.212 lb CO2 per MWh.

For Genesee, the USGS 2015 compilation records 17.61 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Genesee sits within commuting range of roughly 50,092 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Genesee here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Genesee, New York settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Genesee, New York requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Genesee, New York are logged directly below, so each figure on this page can be traced back to its public dataset.