Power by county
New Hanover, NC: data center power outlook
New Hanover, North Carolina is served through an area outside an organized wholesale market, and the figures below describe the public grid around a prospective data center site there. New Hanover carries 55 mapped substations within its boundary, and the highest reachable grid access is 230 kV. Service in New Hanover spans 2 utilities, with DUKE ENERGY PROGRESS - (NC), FOUR COUNTY ELEC MEMBER CORP among those mapped.
Grid position at a glance
- Serving utilities
- DUKE ENERGY PROGRESS - (NC), FOUR COUNTY ELEC MEMBER CORP
- ISO / market
- NON_ISO (Not in an organized wholesale market)
- Highest grid access
- 230 kV
- Substations in county
- 55
- Industrial retail rate
- 7.8¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 2 serving utilities: 6.7 to 7.9¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 482 lb CO2/MWh
- Water withdrawals
- 17 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 30,586 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in New Hanover
What follows is a screening-grade read of New Hanover, North Carolina, built only from named public datasets. At 230 kV, New Hanover sits in the transmission class that a large load would look to. The mapped layer packs 55 substations into New Hanover, a dense spread of options.
Because New Hanover, North Carolina sits outside an organized market, capacity and interconnection are handled by the utility and bilateral deals, not a market operator. For New Hanover, the rate shown is the state industrial average of 7.8 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving New Hanover that report an industrial rate span 2 serving utilities: 6.7 to 7.9¢/kWh, shown as context and never as the county rate.
No interconnection-queue project is on record for New Hanover, North Carolina in the covered feeds, which reflects either genuine quiet or a queue not yet ingested. New Hanover, North Carolina has no EIA-860M generation on file, which reads as zero rather than as a gap. New Hanover sits under a balancing authority that eGRID puts at 481.506 lb CO2 per MWh.
New Hanover withdrew 16.8 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 30,586 people are employed in construction within a 120 km commute of New Hanover (BLS QCEW), which frames staffing distance rather than free labour.
For New Hanover, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for New Hanover, North Carolina describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in New Hanover, North Carolina, a specific address needs its own interconnection study, which this page does not attempt. The figures for New Hanover, North Carolina refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.