Power by county

Surry, NC: data center power outlook

The grid around Surry, North Carolina is summarized here from public data, starting from the county's position in an area outside an organized wholesale market. Inside Surry the mapped layer shows 40 mapped substations, with grid access reaching 230 kV at its strongest point. Retail service across Surry is split among 4 utilities, among them APPALACHIAN POWER CO, BLUE RIDGE ELEC MEMBER CORP - (NC), DUKE ENERGY CAROLINAS, LLC.

Grid position at a glance

Serving utilities
APPALACHIAN POWER CO, BLUE RIDGE ELEC MEMBER CORP - (NC), DUKE ENERGY CAROLINAS, LLC, SURRY-YADKIN ELEC MEMBER CORP
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
230 kV
Substations in county
40
Industrial retail rate
7.8¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 of 4 serving utilities: 7.4 to 14.1¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
485 lb CO2/MWh
Water withdrawals
30 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
74,719 employed in construction within ~120 km (38 of 45 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Surry

Read on for the public power picture of Surry in North Carolina, assembled for data center siting. Transmission-class access reaches 230 kV in Surry at its strongest mapped point. Surry contains 40 mapped substations, a dense footprint that spreads interconnection options across many points.

No organized wholesale market covers Surry, North Carolina, so capacity moves through the local utility and bilateral agreements. Surry carries the state industrial average retail rate of 7.8 cents per kWh from EIA-861, applied statewide. For Surry, the per-utility spread is 3 of 4 serving utilities: 7.4 to 14.1¢/kWh, which qualifies but never replaces the state average.

Surry, North Carolina shows no interconnection-queue project in the covered feeds, whether from real quiet or a feed not yet loaded. No generation is filed as planned or under construction in Surry, North Carolina in the federal EIA-860M inventory, a measured zero rather than missing data. In eGRID, the balancing authority over Surry shows 484.617 lb CO2 per MWh.

For Surry, the USGS 2015 compilation records 29.75 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Surry sits within commuting range of roughly 74,719 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Surry here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Surry, North Carolina settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Surry, North Carolina requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Surry, North Carolina are logged directly below, so each figure on this page can be traced back to its public dataset.

Sources