Power by county

Warren, NC: data center power outlook

Warren sits in the PJM market (PJM Interconnection); what follows is the screening-grade grid picture for Warren, North Carolina, drawn from public datasets. Counting from the mapped infrastructure, Warren holds 18 mapped substations and reaches 500 kV. Warren is covered by 3 retail service territories, including DUKE ENERGY PROGRESS - (NC), HALIFAX ELECTRIC MEMBER CORP, MECKLENBURG ELECTRIC COOPERATIVE.

Grid position at a glance

Serving utilities
DUKE ENERGY PROGRESS - (NC), HALIFAX ELECTRIC MEMBER CORP, MECKLENBURG ELECTRIC COOPERATIVE
ISO / market
PJM (PJM Interconnection)
Highest grid access
500 kV
Substations in county
18
Industrial retail rate
7.8¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
1 of 3 serving utilities: 7.9¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
482 lb CO2/MWh
Water withdrawals
1.7 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
83,064 employed in construction within ~120 km (35 of 38 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Warren

Below, Warren in North Carolina is described from public data as a starting point for siting diligence. Warren reaches 500 kV, a high-voltage transmission class, at its strongest mapped point of grid access. With 18 substations mapped, Warren has a moderate spread of interconnection points.

Warren falls inside the PJM market (PJM Interconnection), which governs how its interconnection requests and capacity move. The rate for Warren is the 7.8 cents per kWh state industrial average (EIA-861), the same figure the map colours by. Across Warren, reported per-utility industrial rates cover 1 of 3 serving utilities: 7.9¢/kWh, offered only as context beneath the state figure.

The covered queue feeds list nothing for Warren, North Carolina, which may be quiet or simply uningested. Nothing is on file for Warren, North Carolina in EIA-860M as planned or under construction, which counts as a measured zero. The balancing authority covering Warren carries a grid carbon intensity of 481.506 lb CO2 per MWh in eGRID.

Reported freshwater withdrawals for all uses in Warren are 1.71 million gallons per day in the USGS 2015 compilation, existing demand rather than water free for a new load. Around Warren, some 83,064 people work in construction within about a 120 km commute (BLS QCEW), a measure of reach, not of available crews.

These numbers for Warren are screening-grade context for the whole county, drawn from public data with the gaps left visible. Read the figures for Warren, North Carolina together rather than one at a time: grid access matters less without substations near it, and a quiet queue reads differently inside an organized market than outside one. The next step for Warren, North Carolina is an address-level interconnection study; the county figures here only narrow where to look. For Warren, North Carolina, the source log below records where each figure comes from and when it was pulled, keeping the provenance visible.

Sources