Power by county

Ashtabula, OH: data center power outlook

The grid around Ashtabula, Ohio is summarized here from public data, starting from the county's position in the PJM market (PJM Interconnection). Inside Ashtabula the mapped layer shows 16 mapped substations, with grid access reaching 345 kV at its strongest point. Retail service across Ashtabula is split among 6 utilities, among them CITY OF CLEVELAND - (OH), CLEVELAND ELECTRIC ILLUM CO, NORTHWESTERN RURAL E C A, INC - (PA).

Grid position at a glance

Serving utilities
CITY OF CLEVELAND - (OH), CLEVELAND ELECTRIC ILLUM CO, NORTHWESTERN RURAL E C A, INC - (PA), OHIO EDISON CO, PENNSYLVANIA ELECTRIC CO, PENNSYLVANIA POWER CO
ISO / market
PJM (PJM Interconnection)
Highest grid access
345 kV
Substations in county
16
Industrial retail rate
8.5¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 of 6 serving utilities: 1.8 to 9.3¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
716 lb CO2/MWh
Water withdrawals
215 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
84,655 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Ashtabula

Read on for the public power picture of Ashtabula in Ohio, assembled for data center siting. At 345 kV, Ashtabula carries high-voltage transmission at its strongest mapped point. Ashtabula contains 16 mapped substations, a moderate footprint spread across the service area.

Wholesale activity over Ashtabula clears through the PJM market (PJM Interconnection), whose footprint sets how interconnection requests and capacity are handled. Ashtabula carries the state industrial average retail rate of 8.5 cents per kWh from EIA-861, applied statewide. For Ashtabula, the per-utility spread is 3 of 6 serving utilities: 1.8 to 9.3¢/kWh, which qualifies but never replaces the state average.

Ashtabula, Ohio has nothing in the interconnection queue across the feeds covered here, quiet or uningested. No generation is filed as planned or under construction in Ashtabula, Ohio in the federal EIA-860M inventory, a measured zero rather than missing data. In eGRID, the balancing authority over Ashtabula shows 716.09 lb CO2 per MWh.

For Ashtabula, the USGS 2015 compilation records 215.18 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Ashtabula sits within commuting range of roughly 84,655 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Ashtabula here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Ashtabula, Ohio settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Ashtabula, Ohio requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Ashtabula, Ohio are logged directly below, so each figure on this page can be traced back to its public dataset.

Sources