Power by county
Montgomery, OH: data center power outlook
For Montgomery, Ohio, the public grid picture begins with its place in the PJM market (PJM Interconnection) and the infrastructure mapped inside the county. Grid access across Montgomery tops out at 345 kV, over a footprint of 58 mapped substations. In Montgomery, 6 utilities share the retail territory, among them BUTLER RURAL ELECTRIC COOP INC - (OH), CITY OF LEBANON - (OH), DAYTON POWER & LIGHT CO.
Grid position at a glance
- Serving utilities
- BUTLER RURAL ELECTRIC COOP INC - (OH), CITY OF LEBANON - (OH), DAYTON POWER & LIGHT CO, DUKE ENERGY OHIO INC, MIDWEST ELECTRIC, INC, PIONEER RURAL ELEC COOP, INC - (OH)
- ISO / market
- PJM (PJM Interconnection)
- Highest grid access
- 345 kV
- Substations in county
- 58
- Industrial retail rate
- 8.5¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 6 serving utilities: 1.8 to 12.4¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 716 lb CO2/MWh
- Water withdrawals
- 89 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 124,538 employed in construction within ~120 km (41 of 45 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Montgomery
This page gathers the public grid evidence for Montgomery, Ohio that bears on a large new load. The highest mapped voltage in Montgomery is 345 kV, in the high-voltage transmission class. Montgomery carries 58 substations, a dense footprint across the county.
For Montgomery, the PJM market (PJM Interconnection) is the operator that handles interconnection and capacity. The state industrial average retail rate is 8.5 cents per kWh, drawn from EIA-861 and applied to Montgomery at the state level rather than as a county rate. The serving utilities in Montgomery that publish a rate range 6 serving utilities: 1.8 to 12.4¢/kWh, a spread kept separate from the state average.
Montgomery, Ohio shows no interconnection-queue project in the covered feeds, whether from real quiet or a feed not yet loaded. The federal EIA-860M inventory files no planned or under-construction generation in Montgomery, Ohio, a real zero rather than a gap. Grid carbon intensity for Montgomery, via its balancing authority, is 716.09 lb CO2 per MWh in eGRID.
USGS 2015 puts freshwater withdrawals across Montgomery at 88.97 million gallons per day for all uses, a measure of use, not spare supply. Within roughly a 120 km commute of Montgomery, about 124,538 people are employed in construction (BLS QCEW), which speaks to how far crews for a multi-year build would travel, not to labour known to be free.
Read the Montgomery figures as screening-grade context: they describe the surrounding grid, not a specific parcel. The numbers for Montgomery, Ohio qualify one another, so grid access, substation density, market membership, and rate are meant to be read as a set, not in isolation. Past this screening view, siting in Montgomery, Ohio turns on a study of a particular address, something no county-level page can stand in for. Every number shown for Montgomery, Ohio traces to a public source listed below, with its retrieval date, so the provenance is auditable rather than asserted.