Power by county

Shelby, OH: data center power outlook

Shelby, Ohio is served through the PJM market (PJM Interconnection), and the figures below describe the public grid around a prospective data center site there. Shelby carries 15 mapped substations within its boundary, and the highest reachable grid access is 765 kV. Service in Shelby spans 9 utilities, with DARKE RURAL ELECTRIC COOP, INC, DAYTON POWER & LIGHT CO, LOGAN COUNTY COOP POWER & LIGHT among those mapped.

Grid position at a glance

Serving utilities
DARKE RURAL ELECTRIC COOP, INC, DAYTON POWER & LIGHT CO, LOGAN COUNTY COOP POWER & LIGHT, MIDWEST ELECTRIC, INC, PIONEER RURAL ELEC COOP, INC - (OH), VILLAGE OF JACKSON CENTER - (OH), VILLAGE OF MINSTER - (OH), VILLAGE OF NEW BREMEN - (OH), VILLAGE OF VERSAILLES - (OH)
ISO / market
PJM (PJM Interconnection)
Highest grid access
765 kV
Substations in county
15
Industrial retail rate
8.5¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 of 9 serving utilities: 1.9 to 9.8¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
716 lb CO2/MWh
Water withdrawals
11 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
107,896 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Shelby

The material below frames Shelby, Ohio for a prospective large load, drawing only on public sources. Grid access in Shelby extends to 765 kV, the extra-high-voltage class. The mapped layer places 15 substations across Shelby, a moderate density.

Interconnection over Shelby runs through the PJM market (PJM Interconnection) and its rules. For Shelby, the rate shown is the state industrial average of 8.5 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Shelby that report an industrial rate span 3 of 9 serving utilities: 1.9 to 9.8¢/kWh, shown as context and never as the county rate.

Across the covered feeds, Shelby, Ohio carries no interconnection-queue project, from either real quiet or a feed not yet loaded. Nothing is on file for Shelby, Ohio in EIA-860M as planned or under construction, which counts as a measured zero. Shelby sits under a balancing authority that eGRID puts at 716.09 lb CO2 per MWh.

Shelby withdrew 10.54 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 107,896 people are employed in construction within a 120 km commute of Shelby (BLS QCEW), which frames staffing distance rather than free labour.

For Shelby, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Shelby, Ohio describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Shelby, Ohio, a specific address needs its own interconnection study, which this page does not attempt. The figures for Shelby, Ohio refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.