Mayes, OK: data center power outlook

Mayes, Oklahoma is served through the SPP market (Southwest Power Pool), and the figures below describe the public grid around a prospective data center site there. Mayes carries 59 mapped substations within its boundary, and the highest reachable grid access is 345 kV. Service in Mayes spans 5 utilities, with CITY OF PRYOR - (OK), GRAND RIVER DAM AUTHORITY, NORTHEAST OKLAHOMA ELECTRIC CO among those mapped.

Grid position at a glance

Serving utilities
CITY OF PRYOR - (OK), GRAND RIVER DAM AUTHORITY, NORTHEAST OKLAHOMA ELECTRIC CO, PUBLIC SERVICE CO OF OKLAHOMA, VERDIGRIS VALLEY ELEC COOP INC
ISO / market
SPP (Southwest Power Pool)
Highest grid access
345 kV
Substations in county
59
Industrial retail rate
6.2¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
4 of 5 serving utilities: 4.9 to 10.1¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
1,042 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
872 lb CO2/MWh
Water withdrawals
58 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
52,142 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Mayes

What follows is a screening-grade read of Mayes, Oklahoma, built only from named public datasets. Grid access in Mayes extends to 345 kV, a high-voltage line class. The mapped layer packs 59 substations into Mayes, a dense spread of options.

Interconnection over Mayes runs through the SPP market (Southwest Power Pool) and its rules. For Mayes, the rate shown is the state industrial average of 6.2 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Mayes that report an industrial rate span 4 of 5 serving utilities: 4.9 to 10.1¢/kWh, shown as context and never as the county rate.

Across the covered feeds, Mayes, Oklahoma carries no interconnection-queue project, from either real quiet or a feed not yet loaded. EIA-860M records 1,041.5 MW planned or under construction for Mayes. Mayes sits under a balancing authority that eGRID puts at 871.526 lb CO2 per MWh.

Mayes withdrew 58.32 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 52,142 people are employed in construction within a 120 km commute of Mayes (BLS QCEW), which frames staffing distance rather than free labour.

For Mayes, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Mayes, Oklahoma describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Mayes, Oklahoma, a specific address needs its own interconnection study, which this page does not attempt. The figures for Mayes, Oklahoma refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.