Clackamas sits in an area outside an organized wholesale market; what follows is the screening-grade grid picture for Clackamas, Oregon, drawn from public datasets. Counting from the mapped infrastructure, Clackamas holds 93 mapped substations and reaches 500 kV. Clackamas is covered by 6 retail service territories, including BONNEVILLE POWER ADMINISTRATION, CANBY UTILITY BOARD, CONSUMERS POWER, INC.
Grid position at a glance
- Serving utilities
- BONNEVILLE POWER ADMINISTRATION, CANBY UTILITY BOARD, CONSUMERS POWER, INC, PACIFICORP, PORTLAND GENERAL ELECTRIC CO, WASCO ELECTRIC COOP, INC
- ISO / market
- NON_ISO (Not in an organized wholesale market)
- Highest grid access
- 500 kV
- Substations in county
- 93
- Industrial retail rate
- 8.3¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 3 of 6 serving utilities: 6.8 to 9.7¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- 200 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 212 lb CO2/MWh
- Water withdrawals
- 281 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 105,201 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Clackamas
Below, Clackamas in Oregon is described from public data as a starting point for siting diligence. Clackamas reaches 500 kV, a high-voltage transmission class, at its strongest mapped point of grid access. With 93 substations mapped, Clackamas offers interconnection points across many locations.
Because Clackamas, Oregon sits outside an organized market, capacity and interconnection are handled by the utility and bilateral deals, not a market operator. The rate for Clackamas is the 8.3 cents per kWh state industrial average (EIA-861), the same figure the map colours by. Across Clackamas, reported per-utility industrial rates cover 3 of 6 serving utilities: 6.8 to 9.7¢/kWh, offered only as context beneath the state figure.
No interconnection-queue project is on record for Clackamas, Oregon in the covered feeds, which reflects either genuine quiet or a queue not yet ingested. Clackamas has 200 MW of planned or under-construction generation on file in EIA-860M. The balancing authority covering Clackamas carries a grid carbon intensity of 212.458 lb CO2 per MWh in eGRID.
Reported freshwater withdrawals for all uses in Clackamas are 280.76 million gallons per day in the USGS 2015 compilation, existing demand rather than water free for a new load. Around Clackamas, some 105,201 people work in construction within about a 120 km commute (BLS QCEW), a measure of reach, not of available crews.
These numbers for Clackamas are screening-grade context for the whole county, drawn from public data with the gaps left visible. Read the figures for Clackamas, Oregon together rather than one at a time: grid access matters less without substations near it, and a quiet queue reads differently inside an organized market than outside one. The next step for Clackamas, Oregon is an address-level interconnection study; the county figures here only narrow where to look. For Clackamas, Oregon, the source log below records where each figure comes from and when it was pulled, keeping the provenance visible.