Power by county

Harney, OR: data center power outlook

Harney, Oregon is served through an area outside an organized wholesale market, and the figures below describe the public grid around a prospective data center site there. Harney carries 22 mapped substations within its boundary, and the highest reachable grid access is 500 kV. Service in Harney spans 6 utilities, with BONNEVILLE POWER ADMINISTRATION, CENTRAL ELECTRIC COOP INC - (OR), HARNEY ELECTRIC COOP, INC among those mapped.

Grid position at a glance

Serving utilities
BONNEVILLE POWER ADMINISTRATION, CENTRAL ELECTRIC COOP INC - (OR), HARNEY ELECTRIC COOP, INC, IDAHO POWER CO, OREGON TRAIL EL CONS COOP, INC, SURPRISE VALLEY ELECTRIFICATION
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
500 kV
Substations in county
22
Industrial retail rate
8.3¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
4 of 6 serving utilities: 6.0 to 11.9¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
212 lb CO2/MWh
Water withdrawals
422 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
No QCEW construction county within commuting rangeA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Harney

The material below frames Harney, Oregon for a prospective large load, drawing only on public sources. Grid access in Harney extends to 500 kV, a high-voltage line class. The mapped layer packs 22 substations into Harney, a dense spread of options.

Because Harney, Oregon sits outside an organized market, capacity and interconnection are handled by the utility and bilateral deals, not a market operator. For Harney, the rate shown is the state industrial average of 8.3 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Harney that report an industrial rate span 4 of 6 serving utilities: 6.0 to 11.9¢/kWh, shown as context and never as the county rate.

No interconnection-queue project is on record for Harney, Oregon in the covered feeds, which reflects either genuine quiet or a queue not yet ingested. EIA-860M lists nothing planned or under construction for Harney, Oregon, which is a national filing and so a real zero. Harney sits under a balancing authority that eGRID puts at 212.458 lb CO2 per MWh.

Harney withdrew 421.6 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. There is no QCEW construction county in commuting range of Harney, Oregon, a fact about staffing a large build.

For Harney, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Harney, Oregon describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Harney, Oregon, a specific address needs its own interconnection study, which this page does not attempt. The figures for Harney, Oregon refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.

Sources