Montgomery, TN: data center power outlook
The grid around Montgomery, Tennessee is summarized here from public data, starting from the county's position in an area outside an organized wholesale market. Inside Montgomery the mapped layer shows 43 mapped substations, with grid access reaching 500 kV at its strongest point. Retail service across Montgomery is split among 5 utilities, among them CITY OF CLARKSVILLE - (TN), CITY OF DICKSON, CUMBERLAND ELEC MEMBER CORP.
Grid position at a glance
- Serving utilities
- CITY OF CLARKSVILLE - (TN), CITY OF DICKSON, CUMBERLAND ELEC MEMBER CORP, MERIWETHER LEWIS ELECTRIC COOP, PENNYRILE RURAL ELECTRIC COOP
- ISO / market
- NON_ISO (Not in an organized wholesale market)
- Highest grid access
- 500 kV
- Substations in county
- 43
- Industrial retail rate
- 6.7¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 4 of 5 serving utilities: 5.9 to 8.0¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 641 lb CO2/MWh
- Water withdrawals
- 24 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 79,348 employed in construction within ~120 km (40 of 41 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Montgomery
The sections below set out what public data shows about siting a large electrical load in Montgomery, Tennessee. At 500 kV, Montgomery carries high-voltage transmission at its strongest mapped point. Montgomery contains 43 mapped substations, a dense footprint that spreads interconnection options across many points.
Montgomery, Tennessee lies outside an organized wholesale market, so generation and transmission are arranged bilaterally and through the local utility rather than a central market operator. Montgomery carries the state industrial average retail rate of 6.7 cents per kWh from EIA-861, applied statewide. For Montgomery, the per-utility spread is 4 of 5 serving utilities: 5.9 to 8.0¢/kWh, which qualifies but never replaces the state average.
For Montgomery, Tennessee, no queued project appears in the feeds currently covered. For Montgomery, Tennessee, the EIA-860M inventory shows no planned or under-construction generation, a measured absence. In eGRID, the balancing authority over Montgomery shows 641.018 lb CO2 per MWh.
For Montgomery, the USGS 2015 compilation records 24.45 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Montgomery sits within commuting range of roughly 79,348 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.
Every figure for Montgomery here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Montgomery, Tennessee settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Montgomery, Tennessee requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Montgomery, Tennessee are logged directly below, so each figure on this page can be traced back to its public dataset.