Power by county
White, TN: data center power outlook
For White, Tennessee, the public grid picture begins with its place in an area outside an organized wholesale market and the infrastructure mapped inside the county. Grid access across White tops out at 500 kV, over a footprint of 4 mapped substations. In White, 5 utilities share the retail territory, among them CANEY FORK ELECTRIC COOP, INC, CITY OF SPARTA, SEQUACHEE VALLEY ELECTRIC COOP.
Grid position at a glance
- Serving utilities
- CANEY FORK ELECTRIC COOP, INC, CITY OF SPARTA, SEQUACHEE VALLEY ELECTRIC COOP, UPPER CUMBERLAND E M C, VOLUNTEER ELECTRIC COOP
- ISO / market
- NON_ISO (Not in an organized wholesale market)
- Highest grid access
- 500 kV
- Substations in county
- 4
- Industrial retail rate
- 6.7¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 5 serving utilities: 6.0 to 8.3¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 641 lb CO2/MWh
- Water withdrawals
- 3.5 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 40,374 employed in construction within ~120 km (34 of 42 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in White
This page gathers the public grid evidence for White, Tennessee that bears on a large new load. The highest mapped voltage in White is 500 kV, in the high-voltage transmission class. White, Tennessee shows 4 substations in the mapped layer, a thin spread across the county.
There is no organized wholesale market over White, Tennessee; arrangements run through the serving utility instead. The state industrial average retail rate is 6.7 cents per kWh, drawn from EIA-861 and applied to White at the state level rather than as a county rate. The serving utilities in White that publish a rate range 5 serving utilities: 6.0 to 8.3¢/kWh, a spread kept separate from the state average.
For White, Tennessee, no queued project appears in the feeds currently covered. No generation is filed as planned or under construction in White, Tennessee in the federal EIA-860M inventory, a measured zero rather than missing data. Grid carbon intensity for White, via its balancing authority, is 641.018 lb CO2 per MWh in eGRID.
USGS 2015 puts freshwater withdrawals across White at 3.45 million gallons per day for all uses, a measure of use, not spare supply. Within roughly a 120 km commute of White, about 40,374 people are employed in construction (BLS QCEW), which speaks to how far crews for a multi-year build would travel, not to labour known to be free.
Read the White figures as screening-grade context: they describe the surrounding grid, not a specific parcel. The numbers for White, Tennessee qualify one another, so grid access, substation density, market membership, and rate are meant to be read as a set, not in isolation. Past this screening view, siting in White, Tennessee turns on a study of a particular address, something no county-level page can stand in for. Every number shown for White, Tennessee traces to a public source listed below, with its retrieval date, so the provenance is auditable rather than asserted.