Andrews, TX: data center power outlook

The grid around Andrews, Texas is summarized here from public data, starting from the county's position in the SPP market (Southwest Power Pool). Inside Andrews the mapped layer shows 18 mapped substations, with grid access reaching 345 kV at its strongest point. Retail service across Andrews is split among 5 utilities, among them LEA COUNTY ELECTRIC COOP, INC, LYNTEGAR ELECTRIC COOP, INC, ONCOR ELECTRIC DELIVERY COMPANY LLC.

Grid position at a glance

Serving utilities
LEA COUNTY ELECTRIC COOP, INC, LYNTEGAR ELECTRIC COOP, INC, ONCOR ELECTRIC DELIVERY COMPANY LLC, SOUTHWESTERN PUBLIC SERVICE CO, TEXAS-NEW MEXICO POWER CO
ISO / market
SPP (Southwest Power Pool)
Highest grid access
345 kV
Substations in county
18
Industrial retail rate
6.5¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 of 5 serving utilities: 4.9 to 8.9¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
9 projects, 2,211 MW
Proposed generation
223 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
734 lb CO2/MWh
Water withdrawals
17 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
25,279 employed in construction within ~120 km (13 of 16 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Andrews

The sections below set out what public data shows about siting a large electrical load in Andrews, Texas. At 345 kV, Andrews carries high-voltage transmission at its strongest mapped point. Andrews contains 18 mapped substations, a moderate footprint spread across the service area.

Wholesale activity over Andrews clears through the SPP market (Southwest Power Pool), whose footprint sets how interconnection requests and capacity are handled. Andrews carries the state industrial average retail rate of 6.5 cents per kWh from EIA-861, applied statewide. For Andrews, the per-utility spread is 3 of 5 serving utilities: 4.9 to 8.9¢/kWh, which qualifies but never replaces the state average.

Andrews carries 9 projects in the interconnection queue, totalling 2,211.18 MW of requested capacity. In Andrews, 222.8 MW is filed as planned or under construction in the federal EIA-860M inventory. In eGRID, the balancing authority over Andrews shows 734.003 lb CO2 per MWh.

For Andrews, the USGS 2015 compilation records 17.36 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Andrews sits within commuting range of roughly 25,279 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Andrews here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Andrews, Texas settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Andrews, Texas requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Andrews, Texas are logged directly below, so each figure on this page can be traced back to its public dataset.