Power by county
Jasper, TX: data center power outlook
The grid around Jasper, Texas is summarized here from public data, starting from the county's position in the MISO market (Midcontinent Independent System Operator). Inside Jasper the mapped layer shows 14 mapped substations, with grid access reaching 500 kV at its strongest point. Retail service across Jasper is split among 9 utilities, among them CITY OF JASPER - (TX), DEEP EAST TEXAS ELEC COOP INC, ENTERGY TEXAS INC..
Grid position at a glance
- Serving utilities
- CITY OF JASPER - (TX), DEEP EAST TEXAS ELEC COOP INC, ENTERGY TEXAS INC., HOUSTON COUNTY ELEC COOP INC, JASPER-NEWTON ELEC COOP, INC, KIRBYVILLE LIGHT & POWER CO, ONCOR ELECTRIC DELIVERY COMPANY LLC, SAM HOUSTON ELECTRIC COOP INC, SAM RAYBURN MUNICIPAL PWR AGNY
- ISO / market
- MISO (Midcontinent Independent System Operator)
- Highest grid access
- 500 kV
- Substations in county
- 14
- Industrial retail rate
- 6.5¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 5 of 9 serving utilities: 5.9 to 9.0¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- 4 projects, 409 MW
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 982 lb CO2/MWh
- Water withdrawals
- 49 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 38,845 employed in construction within ~120 km (18 of 20 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Jasper
Read on for the public power picture of Jasper in Texas, assembled for data center siting. At 500 kV, Jasper carries high-voltage transmission at its strongest mapped point. Jasper contains 14 mapped substations, a moderate footprint spread across the service area.
Wholesale activity over Jasper clears through the MISO market (Midcontinent Independent System Operator), whose footprint sets how interconnection requests and capacity are handled. Jasper carries the state industrial average retail rate of 6.5 cents per kWh from EIA-861, applied statewide. For Jasper, the per-utility spread is 5 of 9 serving utilities: 5.9 to 9.0¢/kWh, which qualifies but never replaces the state average.
Jasper carries 4 projects in the interconnection queue, totalling 409.2 MW of requested capacity. For Jasper, Texas, the EIA-860M inventory shows no planned or under-construction generation, a measured absence. In eGRID, the balancing authority over Jasper shows 981.982 lb CO2 per MWh.
For Jasper, the USGS 2015 compilation records 48.92 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Jasper sits within commuting range of roughly 38,845 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.
Every figure for Jasper here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Jasper, Texas settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Jasper, Texas requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Jasper, Texas are logged directly below, so each figure on this page can be traced back to its public dataset.