Power by county

Lipscomb, TX: data center power outlook

Lipscomb, Texas is served through the SPP market (Southwest Power Pool), and the figures below describe the public grid around a prospective data center site there. Lipscomb carries 8 mapped substations within its boundary, and the highest reachable grid access is 138 kV. Service in Lipscomb spans 6 utilities, with GREENBELT ELECTRIC COOP, INC, NORTH PLAINS ELECTRIC COOP INC, NORTHWESTERN ELECTRIC COOP INC - (OK) among those mapped.

Grid position at a glance

Serving utilities
GREENBELT ELECTRIC COOP, INC, NORTH PLAINS ELECTRIC COOP INC, NORTHWESTERN ELECTRIC COOP INC - (OK), OKLAHOMA GAS & ELECTRIC CO, SOUTHWESTERN PUBLIC SERVICE CO, TRI-COUNTY ELECTRIC COOP, INC (OK)
ISO / market
SPP (Southwest Power Pool)
Highest grid access
138 kV
Substations in county
8
Industrial retail rate
6.5¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
4 of 6 serving utilities: 4.9 to 15.9¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
872 lb CO2/MWh
Water withdrawals
32 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
2,602 employed in construction within ~120 km (13 of 18 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Lipscomb

The material below frames Lipscomb, Texas for a prospective large load, drawing only on public sources. At 138 kV, Lipscomb sits in the transmission class that a large load would look to. The mapped layer places 8 substations across Lipscomb, a moderate density.

Interconnection over Lipscomb runs through the SPP market (Southwest Power Pool) and its rules. For Lipscomb, the rate shown is the state industrial average of 6.5 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Lipscomb that report an industrial rate span 4 of 6 serving utilities: 4.9 to 15.9¢/kWh, shown as context and never as the county rate.

Across the covered feeds, Lipscomb, Texas carries no interconnection-queue project, from either real quiet or a feed not yet loaded. EIA-860M lists nothing planned or under construction for Lipscomb, Texas, which is a national filing and so a real zero. Lipscomb sits under a balancing authority that eGRID puts at 871.526 lb CO2 per MWh.

Lipscomb withdrew 32.27 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 2,602 people are employed in construction within a 120 km commute of Lipscomb (BLS QCEW), which frames staffing distance rather than free labour.

For Lipscomb, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Lipscomb, Texas describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Lipscomb, Texas, a specific address needs its own interconnection study, which this page does not attempt. The figures for Lipscomb, Texas refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.

Sources