Llano, TX: data center power outlook
Llano, Texas is served through the ERCOT market (Electric Reliability Council of Texas), and the figures below describe the public grid around a prospective data center site there. Llano carries 12 mapped substations within its boundary, and the highest reachable grid access is 138 kV. Service in Llano spans 6 utilities, with AEP TEXAS NORTH COMPANY, CENTRAL TEXAS ELEC COOP, INC, CITY OF LLANO - (TX) among those mapped.
Grid position at a glance
- Serving utilities
- AEP TEXAS NORTH COMPANY, CENTRAL TEXAS ELEC COOP, INC, CITY OF LLANO - (TX), HAMILTON COUNTY ELEC COOP ASSN, ONCOR ELECTRIC DELIVERY COMPANY LLC, PEDERNALES ELECTRIC COOP, INC
- ISO / market
- ERCOT (Electric Reliability Council of Texas)
- Highest grid access
- 138 kV
- Substations in county
- 12
- Industrial retail rate
- 6.5¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 2 of 6 serving utilities: 6.4 to 6.7¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 734 lb CO2/MWh
- Water withdrawals
- 103 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 106,577 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Llano
What follows is a screening-grade read of Llano, Texas, built only from named public datasets. At 138 kV, Llano sits in the transmission class that a large load would look to. The mapped layer places 12 substations across Llano, a moderate density.
Interconnection over Llano runs through the ERCOT market (Electric Reliability Council of Texas) and its rules. For Llano, the rate shown is the state industrial average of 6.5 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Llano that report an industrial rate span 2 of 6 serving utilities: 6.4 to 6.7¢/kWh, shown as context and never as the county rate.
Across the covered feeds, Llano, Texas carries no interconnection-queue project, from either real quiet or a feed not yet loaded. Nothing is on file for Llano, Texas in EIA-860M as planned or under construction, which counts as a measured zero. Llano sits under a balancing authority that eGRID puts at 734.003 lb CO2 per MWh.
Llano withdrew 102.9 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 106,577 people are employed in construction within a 120 km commute of Llano (BLS QCEW), which frames staffing distance rather than free labour.
For Llano, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Llano, Texas describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Llano, Texas, a specific address needs its own interconnection study, which this page does not attempt. The figures for Llano, Texas refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.